CR 2013-013 Accept Improvements and Authorize Final Payment - 2011 Street and Utility ImprovementsCa
City of Hopkins
February 5, 2013 Council Report 2013-013
Accept Improvements and Authorize Final Payment
2011 Street and Utility Improvements
City Proiect 2010-10
Proposed Action
Staff recommends approval of the following motion: adopt Resolution 2013-006, accepting
improvements and authorizing final payment, 5h Street South Street and Utility Improvements,
City Project 2010-10.
Overview
The contractor has completed all work detailed in the contract as well as any punch list items to
the City's satisfaction. This action completes an assessable street project. Staff recommends
approval of Resolution 2013-006 accepting the improvements and authorizing the final payment
in the amount of $1,000.00.
Supporting Documents
• Final pay request
• Resolution 2013-006
R. Bradford, P.E.
City Engineer
Financial Impact: $1,000.00 Budgeted Y/N Y Source: MSA, PIR, Utility Funds,
Assessments Related Documents (CIP, ERP, etc.): CIP, Feasibility Study
Notes:
E:\Council Reports\2013\CR2013-013 Accept Improvements 2011 Street Improvements.doc
CONTRACTOR'S FINAL PAY REQUEST NO. 8
DISTRIBUTION:
2011 STREET & UTILITY IMPROVEMENTS
CONTRACTOR (2)
OWNER (2)
CITY PROJECT NO. 10-10
ENGINEER (1)
CITY OF HOPKINS, MN
IBMI PROJECT NO. T16.102570
TOTAL AMOUNT BID PLUS APPROVED CHANGE ORDERS
$1,870,114.35
TOTAL, COMPLETED WORK TO DATE
$1,758,003.79
RETAINED PERCENTAGE ( 0%)
$0.00
TOTAL AMOUNT OF OTHER PAYMENTS OR (DEDUCTIONS)
($2,028.00)
$2/cy deduct for topsoil (1014 cy total)
NET AMOUNT DUE TO CONTRACTOR TO DATE
$1,755,975.79
TOTAL AMOUNT PAID ON PREVIOUS ESTIMATES
$1,754,975.79
PAY CONTRACTOR AS ESTIMATE NO. 7
$1,000.00
Certificate for Final Payment
I hereby certify that, to the best of my knowledge and belief, all items quantities and prices
of work and material shown on this Estimate are correct and that all work has been
performed in full accordance with the terms and conditions of the Contract for this project
between the Owner and the undersigned Contractor, and as amended by any
authorized changes, and that the foregoing is a true and correct statement of the amount
for the Final Estimate, that the provisions of M. S. 290.92 have been complied with and that
all claims against me by reason of the Contract have been paid or satisfactorily secured.
Contractor: Midwest Asphalt Corporation
P.O. Box 5477
Hopkins, MN 55343
_-
(-- y (/ - Name Title
Date SHIRLEY M. EIDEV,
SECRETARY
Approved
Contractor's Surety
CHECKED AND APPROVED AS TO QUANTITIES AND AMOUNT:
ENGINEER: BOL ON & MENK,, INC., 12224 NICOLLET AVENUE, BURNSVILLE, MN 55337.
By Z1 f �'� PROJECT ENGINEER
Date A 3
APPROVED FOR PAYMENT:
OWNER:
By
Name Title Date
And
Name Title Date
Final Pay Estimate No.:
2011 STREET & UTILITY IMPROVEMENTS
CITY PROJECT NO. 10-10
CITY OF HOPKINS, MN
BMI PROJECT NO. T16.102570
WORK COMPLETED THROUGH NOVEMBER 16. 2012
ITEM
NO.
ITEM
UNIT
PRICE
AS BID
ESTIMATED
QUANTITY-
ESTIMATED .
AMOUNT
PREVIOUS ESTIMATE
ESTIMATEDESTIMATED
QUANTITY AMQUNT
COMPLETED TO DATE
ESTIMATED ESTIMATED
QUANTITY AMOUNT
1
MOBILIZATION
$65,000.00
1 LUMP SUM
$65,000.00
1.00 LUMP SUM
$65,000.00
1.00 LUMP SUM
$65,000.00
2
CLEAR AND GRUB TREE
$255.00
15
EACH
$3,825.00
18
EACH
$4,590.00
18
EACH
$4,590.00
3
REMOVE BITUMINOUS CURB
$0.45
2710
LIN FT
$1,219.50
2,379
LIN FT
$1,070.55
2,379
LIN FT
$1,070.55
4
REMOVE CONCRETE BLOCK CURBING
$2.50
755
LIN FT
$1,887.50
1,463
LIN FT
$3,657.50
1,463
LIN FT
$3,657.50
5
REMOVE B618 CONCRETE CURB AND GUTTER
$2.80
6540
LIN FT
$18,312.00
5,113
LIN FT
$14,316.40
5,113
LIN FT
$14,316.40
6
MILL BITUMINOUS PAVEMENT FULL -DEPTH
$2.00
29256
SQ YD
$58,512.00
29,256
SQ YD
$58,512.00
29,256
SQ YD
$58,512.00
7
MILL BITUMINOUS PAVEMENT 2" DEPTH
$10.00
690
SQ YD
$6,900.00
720
SQ YD
$7,200.00
720
SQ YD
$7,200.00
8
REMOVE BITUMINOUS PAVEMENT DRIVEWAYS/TRAIL
$3.001
982
SQ YD
$2,946.00
1,068
SQ YD
$3,204.00
1,068
SQ YD
$3,204.00
9
REMOVE CONCRETE PAVEMENT WALK/DRIVEWAYNALLEY GU
$6.00
2323
SQ YD
$13,938.00
1,465
SQ YD
$8,790.00
1,465
SQ YD
$8,790.00
10
SAW -CUT BITUMINOUS PAVEMENT
$3.00
755
LIN FT
$2,265.00
155
LIN FT
$465.00
155
LIN FT
$465.00
11
SAW -CUT CONCRETE PAVEMENT
$5.00
1178
LIN FT
$5,890.00
1,353
LIN FT
$6,765.00
1,353
LIN FT
$6,765.00
12
BITUMINOUS WEAR COURSE STREETS SPWEB340C
$100.00
90
TON
$9,000.00
115
TON
$11,500.00
115
TON
$11,500.00
13
BITUMINOUS WEAR COURSE STREETS SPWEA240C
$65.00
2650
TON
$172,250.00
2,676
TON
$173,940.00
2,676
TON
$173,940.00
14
BITUMINOUS NON WEAR COURSE STREETS SPNWB2306
$54.00
3520
TON
$190,080.00
3,753
TON
$202,662.00
3,753
TON
$202,662.00
15
BITUMINOUS MATERIAL FOR TACK COAT
$3.00
1760
GAL
$5,280.00
1,060
GAL
$3,180.00
1,060
GAL
$3,180.00
16
3" BITUMINOUS DRIVEWAY & TRAIL PAVEMENT SPWEA240C
$23.00
716
SQ YO
$16,468.00
856
SQ YD
$19,688.00
856
SQ YD
$19,688.00
17
TEMPORARY BITUMINOUS CURB EDGE TRANSITION
$5.001
1040
LIN FT
$5,200.00
LIN FT
LIN FT
18
AGGREGATE BASE CLASS 5
$7.50
19399
TON
$145,492.50
16,170
TON
$121,275.00
16,170
TON
$121,275.00
19
AGGREGATE BASE CLASS 2 DRIVEWAY & TRAIL SURFACING
$30.00
138
TON
$4,140.00
48
TON
$1,440.00
48
TON
$1,440.00
20
SELECT GRANULAR BORROW
$18.00
2470
CU YD
$44,460.00
1,218
CU YD
$21,924.00
1,218
CU YD
$21,924.00
21
SUBGRADE EXCAVATION
$12.00
2470
CU YD
$29,640.00
2,911
CU YD
$34,932.00
2,911
CU YD
$34,932.00
22
COMMON EXCAVATION
$11.75
10929
CU YD
$128,415.75
10,929
CU YD
$128,415.75
10,929
CU YD
$128,415.75
23
EXPLORATORY EXCAVATION
$110.00
32
HOUR
$3,520.00
23
HOUR
$2,475.00
23
HOUR
$2,475.00
24
MODULAR BLOCK RETAINING WALL
$41.00
70
SQ FT
$2,870.00
53
SQ FT
$2,173.00
53
SQ FT
$2,173.00
25
4" CONCRETE WALK
$3.501
15596
SQ FT
$54,586.00
14,044
SQ FT
$49,154.00
14,044
SQ FT
$49,154.00
26
B618 CONCRETE CURB & GUTTER
$9.30
8990
LIN FT
$83,607.00
9,943
LIN FT
$92,469.90
9,943
LIN FT
$92,469.90
27
B618 CONCRETE CURB & GUTTER - SPOT REPLACEMENT
$18.00
1381
LIN FT
$24,858.00
669
LIN FT
$12,042.00
669
LIN FT
$12,042.00
28
B618 CONCRETE CURB & GUTTER - WATER SERVICE REPLACEP
$18.00
1425
LIN FT
$25,650.00
751
LIN FT
$13,518.00
751
LIN FT
$13,518.00
29
6" RESIDENTIAL CONCRETE DRIVEWAY PAVEMENT
$45.00
925
SQ YD
$41,625.00
919
SO YD
$41,355.00
919
SQ YD
$41,355.00
30
7" CONCRETE CROSS GUTTER
$50.00
85
SQ YO
$4,250.00
43
SQ YD
$2,150.00
43
SQ YD
$2,150.00
31
8" COMMERCIAL CONCRETE DRIVEWAY PAVEMENT
$52.00
209
SQ YD
$10,868.00
179
SQ YD
$9,308.00
179
SQ YD
$9,308.00
32
10" CONCRETE STREET PAVEMENT
$255.00
40
CU YD
$10,200.00
37
CU YD
$9,435.00
37
CU YD
$9,435.00
33
ADJUST CASTING
$650.001
17
EACH
$11,050.00
8
EACH
$5,200.00
8
EACH
$5,200.00
34
NEENAH R-1733 SANITARY SEWER MH CASTING ASSEMBLY
$950.00
29
EACH
$27,550.00
26
EACH
$24,700.00
26
EACH
$24,700.00
35
NEENAH R-1733 STORM SEWER MH CASTING ASSEMBLY
$800.00
15
EACH
$12,000.00
15
EACH
$12,000.00
15
EACH
$12,000.00
36
NEENAH R -3067V STORM SEWER CB CASTING ASSEMBLY
$500.00
20
EACH
$10,000.00
26
EACH
$13,000.00
26
EACH
$13,000.00
37
NEENAH R-2540 STORM SEWER CB CASTING ASSEMBLY
$550.00
4
EACH
$2,200.00
3
EACH
$1,650.00
3
EACH
$1,650.00
38
NEENAH R -3462-B STORM SEWER CB CASTING ASSEMBLY
$650.00
2
EACH
$1,300.00
EACH
EACH
39
TRAFFIC CONTROL
$8,800.00
1.00 LUMP SUM
$8,800.00
1.00 LUMP SUM
$8,800.00
1.00 LUMP SUM
$8,800.00
40
4" BROKEN LINE YELLOW - EPDXY
$0.10
480
LIN FT
$48.00
435
LIN FT
$43.50
435
LIN FT
$43.50
41
4" SOLID LINE YELLOW - EPDXY
$0.401
140
LIN FT
$56.00
140
LIN FT
$56.00
140
LIN FT
$56.00
42
4" DOUBLE SOLID LINE YELLOW - EPDXY
$0.80
142
LIN FT
$113.60
115
LIN FT
$92.00
115
LIN FT
$92.00
43
12" SOLID LINE YELLOW - EPDXY
$5.00
50
LIN FT
$250.00
39
LIN FT
$195.00
39
LIN FT
$195.00
44
CROSSWALK BLOCK WHITE - EPDXY
$80.00
49
EACH
$3,920.00
29
EACH
$2,320.00
29
EACH
$2,320.00
45
TRUNCATED DOMES PEDESTRIAN RAMPS
$30.00
424
SQ FT
$12,720.00
300
SQ FT
$9,000.00
300
SQ FT
$9,000.00
46
ORANGE CONSTRUCTION FENCE W/ POSTS
$2.25
830
LIN FT
$1,867.50
671
LIN FT
$1,509.75
671
LIN FT
$1,509.75
47
SILT FENCE
$3.00
2812
LIN FT
$8,436.00
1,992
LIN FT
$5,976.00
1,992
LIN FT
$5,976.00
48
INLET PROTECTION
$140.00
59
EACH
$8,260.00
44
EACH
$6,160.00
44
EACH
$6,160.00
49
PREMIUM TOPSOIL BORROW
$13.001
1800
CU YD
$23,400.00
1,014
CU YD
$13,182.00
1,014
CU YD
$13,182.00
50
LAWN TYPE SOD
$3.80
6770
SQ YD
$25,726.00
6,292
SQ YD
$23,909.60
6,292
SQ YD
$23,909.60
51
SALT RESISTANT SOD
$4.00
450
SQ YD
$1,800.00
SQ YD
SQ YD
52
ISEED MIXTURE 240
$3.001
80
LB
$240.00
16
LB
$48.00
16
LB
$48.00
Final Pay Estimate No.:
2011 STREET & UTILITY IMPROVEMENTS
CITY PROJECT NO. 10-10
CITY OF HOPKINS, MN
BMI PROJECT NO. T16.102570
WORK COMPLETED THROUGH NOVEMBER 16. 2012
ITEM
NO.
53
ITEM
SEED MIXTURE 260
UNIT
PRICE
$2.00
AS BID
ESTIMATED
QUANTITY
110 LB
ESTIMATED
AMOUNT
$220.00
PPREVIOUS ESTIMATE I
ESTIMATED ESTIMATED
QUANTITY AMOUNT
70 LB $140.00
COMPLETED TO DATE
ESTIMATED: " ESTIMATED
QUANTITY AMOUNT
70 LB $140.00
54
CATEGORY 1 EROSION CONTROL BLANKET
$2.50
2718
SO YD
$6,795.00
4,064
SQ YD
$10,160.00
4,064
SQ YD
$10,160.00
55
CATEGORY 5 EROSION CONTROL BLANKET
$3.00
962
SQ YD
$2,886.00
650
SQ YD
$1,950.00
650
SQ YD
$1,950.00
56
PRIVATE LANDSCAPING ALLOWANCE SPRINKLERS, TREES, MI
$25,000.001
1.00 LUMP SUM
$25,000.00
0.6965 LUMP SUM
$17,412.34
0.6965 LUMP SUM
$17,412.34
57
DECIDUOUS TREE - 2" B&B SUGAR MAPLE
$270.00
3
EACH
$810.00
1
EACH
$270.00
1
EACH
$270.00
58
DECIDUOUS TREE - 2" B&B WHITE OAK
$270.00
3
EACH
$810.00
1
EACH
$270.00
1
EACH
$270.00
59
DECIDUOUS TREE - 2" B&B PARKWAY NORWAY MAPLE
$240.00
3
EACH
$720.00
4
EACH
$960.00
4
EACH
$960.00
60
DECIDUOUS TREE - 2" B&B RED OAK
$270.00
3
EACH
$810.00
1
EACH
$270.00
1
EACH
$270.00
61
DECIDUOUS TREE - 2" B&B GREENSPIRE LINDEN
$250.00
3
EACH
$750.00
1
EACH
$250.00
1
EACH
$250.00
62
DECIDUOUS TREE - 2" B&B CATHEDRAL ELM - DISEASE RESIST
$270.00
5
EACH
$1,350.00
7
EACH
$1,890.00
7
EACH
$1,890.00
63
SALVAGE & REINSTALL TRAFFIC SIGNS
$4,400.00
1.00 LUMP SUM
$4,400.00
1.00 LUMP SUM
$4,400.00
1.00 LUMP SUM
$4,400.00
64
RELOCATE PARK LIGHTING ELECTRICAL CONTROL PANEL
$2,500,001
1.00 LUMP SUM
$2,500.00
1.00 LUMP SUM
$2,500.00
1.00 LUMP SUM
$2,500.00
65
REMOVE SANITARY MANHOLE
$360.001
9
EACH
$3,240.00
9
EACH
$3,240.00
9
EACH
$3,240.00
66
REMOVE SANITARY SEWER MAIN
$3.001
280
LF
$840.00
387
LF
$1,161.00
387
LF
$1,161.00
67
8"X6" PVC WYE
$85.001
12
EACH
$1,020.00
13
EACH
$1,105.00
13
EACH
$1,105.00
68
10"X6" PVC WYE
$150.00
1
EACH
$150.00
1
EACH
$150.00
1
EACH
$150.00
69
6" PVC PIPE SEWER SERVICE SANITARY
$23.00
435
LF
$10,005.00
405
LF
$9,315.00
405
LF
$9,315.00
70
8" PVC PIPE SEWER SANITARY
$22.00
295
LF
$6,490.00
319
IF
$7,018.00
319
LF
$7,018.00
71
10" PVC PIPE SEWER SANITARY
$105.00
10
LF
$1,050.00
10
LF
$1,050.00
10
LF
$1,050.00
72
8" DI PIPE SEWER SANITARY
$41.00
20
LF
$820.00
20
LF
$820.00
20
LF
$820.00
73
48" SANITARY SEWER MANHOLE
$2,400.00
8
EACH
$19,200.00
8
EACH
$19,200.00
8
EACH
$19,200.00
74
60" SANITARY SEWER MANHOLE
$4,000.00
1
EACH
$4,000.00
1
EACH
$4,000.00
1
EACH
$4,000.00
75
CONNECT TO EXISTING SANITARY SEWER PIPE
$110.00
20
EACH
$2,200.00
20
EACH
$2,200.00
20
EACH
$2,200.00
76
CONNECT TO EXISTING SANITARY SEWER SERVICE PIPE
$130.00
14
EACH
$1,820.00
37
EACH
$4,810.00
37
EACH
$4,810.00
77
6" PVC SERVICE CLEANOUT
$210.00
3
EACH
$630.00
2
EACH
$420.00
2
EACH
$420.00
78
RECONSTRUCT SANITARY MANHOLE INVERT
$665.00
2
EACH
$1,330.00
3
EACH
$1,995.00
3
EACH
$1,995.00
79
REMOVE HYDRANT & VALVE
$260.00
13
EACH
$3,380.00
13
EACH
$3,380.00
13
EACH
$3,380.00
80
REMOVE MAINLINE VALVE
$51.00
9
EACH
$459.00
8
EACH
$408.00
8
EACH
$408.00
81
REMOVE 3" SERVICE VALVE
$1,000.00
1 LUMP SUM
$1,000.00
1.00 LUMP SUM
$1,000.00
1.00 LUMP SUM
$1,000.00
82
REMOVE WATERMAIN
$1.00
257
LF
$257.00
208
LF
$208.00
208
LF
$208.00
83
REMOVE EXISTING CORPORATION STOP
$260.00
5
EACH
$1,300.00
3
EACH
$780.00
3
EACH
$780.00
84
ADJUST VALVE BOX
$185.00
4
EACH
$740.00
6
EACH
$1,110.00
6
EACH
$1,110.00
85
CONNECT TO EXISTING WATERMAIN
$310.00
23
EACH
$7,130.00
28
EACH
$8,680.00
28
EACH
$8,680.00
86
HYDRANT
$3,500.00
14
EACH
$49,000.00
14
EACH
$49,000.00
14
EACH
$49,000.00
87
6" DI PIPE WATERMAIN
$22.00
598
LIN FT
$13,156.00
643
LIN FT
$14,146.00
643
LIN FT
$14,146.00
88
6" GATE VALVE & BOX
$1,550.00
24
EACH
$37,200.00
26
EACH
$40,300.00
26
EACH
$40,300.00
89
16" BUTTERFLY VALVE & BOX
$5,000.00
1
EACH
$5,000.00
EACH
EACH
90
TEMPORARY WATER SERVICE
$400.001
2
EACH
$800.00
2
EACH
$800.00
2
EACH
$800.00
91
1" CORPORTATION STOP & BOX
$205.00
2
EACH
$410.00
6
EACH
$1,230.00
6
EACH
$1,230.00
92
1" TYPE K COPPER
$19.50
3550
LIN FT
$69,225.00
3,586
LIN FT
$69,927.00
3,586
LIN FT
$69,927.00
93
1" CURB STOP & BOX
$500.00
111
EACH
$55,500.00
111
EACH
$55,500.00
111
EACH
$55,500.00
94
CONNECT TO EXISTING WATER SERVICE
$300.00
109
EACH
$32,700.00
110
EACH
$33,000.00
110
EACH
$33,000.00
95
DUCTILE IRON FITTINGS
$6.00
1648
LBS
$9,888.00
1,342
LBS
$8,052.00
1,342
LBS
$8,052.00
96
4" POLYSTYRENE INSULATION
$2.00
308
SQ FT
$616.00
184
SO FT
$368.00
184
SQ FT
$368.00
97
REMOVE SEWER PIPE STORM
$5.00
950
LIN FT
$4,750.00
935
LIN FT
$4,675.00
935
LIN FT
$4,675.00
98
REMOVE DRAINAGE STRUCTURE
$230.001
15
EACH
$3,450.00
13
EACH
$2,990.00
13
EACH
$2,990.00
99
RECONSTRUCT CATCH BASIN
$510.00
4
EACH
$2,040.00
6
EACH
$3,060.00
6
EACH
$3,060.00
100
6" PVC PIPE SEWER STORM
$95.00
15
LIN FT
$1,425.00
LIN FT
LIN FT
101
12" DI PIPE SEWER STORM
$56.00
131
LIN FT
$7,336.00
127
LIN FT
$7,112.00
127
LIN FT
$7,112.00
102
12" PVC PIPE SEWER STORM
$32.00
65
LIN FT
$2,080.00
63
LIN FT
$2,016.00
63
LIN FT
$2,016.00
103
12" RC PIPE SEWER CL V DESIGN 3006 STORM
$33.00
535
LIN FT
$17,655.00
549
LIN FT
$18,117.00
549
LIN FT
$18,117.00
104
15" RC PIPE SEWER CL V DESIGN 3006 STORM
$23.00
694
LIN FT
$15,962.001
681
LIN FT
$15,663.00
681
LIN FT
$15,663.00
105
18" RC PIPE SEWER CL V DESIGN 3006 STORM
$29.00
170
LIN FT
$4,930.001
170
LIN FT
$4,930.00
170
LIN FT
$4,930.00
Final Pay Estimate No.: 8
2011 STREET & UTILITY IMPROVEMENTS
CITY PROJECT NO. 10-10
CITY OF HOPKINS, MN
BMI PROJECT NO. T16.102570
WORK COMPLETED THROUGH NOVEMBER 16, 2012
ITEM
NO.
ITEM
21" RC PIPE SEWER CL III DESIGN 3006 STORM
UNIT
PRICE
$41.00
AS BID
ESTIMATED ESTIMATED
QUANTITY AMOUNT
22 LIN FT $902.00
PREVIOUS ESTIMATE
ESTIMATED ESTIMATED
QUANTITY '' AMOUNT
22 LIN FT $902.00
COMPLETED TO DATE
ESTIMATED ESTIMATED
QUANTITY AMOUNT
22 LIN FT $902.00
$1,035.00
CONNECT TO EXISTING STORM PIPE
$275.00
13
EACH
$3,575.00
14
EACH
$3,850.00
14
EACH
$3,850.00
SUPPLEMENTAL AGREEMENT NO. 1 TOTAL
CONNECT TO EXISTING STORM STRUCTURE
$275.00
6
EACH
$1,650.00
6
EACH
$1,650.00
6
EACH
$1,650.00
1 LUMP SUM
CONSTRUCT DRAINAGE STRUCTURE DESIGN G
$700.00
4
EACH
$2,800.00
4
EACH
$2,800.00
4
EACH
$2,800.00
R10
CONSTRUCT DRAINAGE STRUCTURE DESIGN R-1 2'x3'
$630.00
17
EACH
$10,710.00
19
EACH
$11,970.00
19
EACH
$11,970.00
$295.00
CONSTRUCT DRAINAGE STRUCTURE DESIGN 4020-48"
$1,150.00
11
EACH
$12,650.00
11
EACH
$12,650.00
11
EACH
$12,650.00
1 LUMP SUM
CONSTRUCT DRAINAGE STRUCTURE DESIGN 4022-48"
$1,150.00
2
EACH
$2,300.00
2
EACH
$2,300.00
2
EACH
$2,300.00
$592.00
TOTAL ORIGINAL CONTRACT AMOUNT:
REUSE EX 30" RCP - INSTALL TIEBACKS
$95.00
20 LIN FT
$1,834,714.35
20 LIN FT
$1,900.00
$1,733,979.29
$1,900.00
7
$1,733,979.29
SUPPLEMENTAL AGREEMENT NO. 1 - WET TAP
4" EXPOSED AGGREGATE CONCRETE WALK
$17.25
64 SF
$1,104.00
60 SF
$1,035.00
60 SF
1
16" X 6" WET TAP
$6,300.00
1 LUMP SUM
$6,300.00
1 LUMP SUM
$6,300.00
1 LUMP SUM
$6,300.00
$2,375.00
SUPPLEMENTAL AGREEMENT NO. 1 TOTAL
MISCELLANOUS CASTINGS PER INVOICE ON 8/3/11
$4,994.99
$6,300.00
$4,994.99
$6,300.00
$4,994.99
$6,300.00
SUPPLEMENTAL AGREEMENT NO. 2 - BACKWASH POND IMPROVEMENTS
7
LANDSCAPING REPAIRS AS OF 10/11/2011
$1,879.34
1 LUMP SUM
$1,879.34
1 LUMP SUM
$1,879.34
1
MOBILIZATION
$1,000.00 1
1 LUMP SUM
$1,000.00
1 LUMP SUM
$1,000.00
1 LUMP SUM
$1,000.00
2
REMOVE EXISTING MANHOLE
$1,250.00
1 EACH
$1,250.00
1 EACH
$1,250.00
1 EACH
$1,250.00
3
CONSTRUCT 60" DIA STORM MANHOLE
$295.00
10 LIN FT
$2,950.00
8.5 LIN FT
$2,507.50
8.5 LIN FT
$2,507.50
4
CLEAN OUT OUTLET ADD 8" PVC 90 DEG BEND
$1,200.00
1 LUMP SUM
$1,200.00
1 LUMP SUM
$1,200.00
1 LUMP SUM
$1,200.00
5
FILL AND COMPACT TO ORIGINAL DESIGN
$16.00
200 CU YD
$3,200.00
37 CU YD
$592.00
37 CU YD
$592.00
6
REUSE EX 30" RCP - INSTALL TIEBACKS
$95.00
20 LIN FT
$1,900.00
20 LIN FT
$1,900.00
20 LIN FT
$1,900.00
7
CONNECT TO EXISTING STRUCTURE
$950.00
2 EACH
$1,900.00
2 EACH
$1,900.00
2 EACH
$1,900.00
8
SEED MIX NO. 325 PRAIRIE STYLE GRASS
$80.00
20 LBS
$1,600.00
LBS
LBS
9
SILT FENCE
$3.00
250 LIN FT
$750.00
LIN FT
LIN FT
10
CATEGORY 5 EROSION CONTROL BLANKET
$3.00
970 SQ YD
$2,910.00
SQ YD
SQ YD
11
PREMIUM TOPSOIL BORROW
$13.00
130 CU YD
$1,690.00
CU YD
CU YD
12
SALVAGE & REINSTALL 8' CHAIN LINK FENCE
$25.00
250 LIN FT
$6,250.00
195 LIN FT
$4,875.00
195 LIN FT
$4,875.00
13
RIP RAP
$250.00
10 CU YD
$2,500.00
10 CU YD
$2,500.00
10 CU YD
$2,500.00
SUPPLEMENTAL AGREEMENT NO. 2 TOTAL
LANDSCAPING ALLOWANCE BREAKDOWN (BREAKDOWN OF ITEM NO. 56)
$29,100.00
$17,724.50
$17,724.50
1
CONCRETE STEPS
$215.00
16.5 LF
$3,547.50
16.5 LF
$3,547.50
16.5 LF
$3,547.50
2
4" CONCRETE WALK
$4.75
109 SF
$517.75
109 SF
$517.75
109 SF
$517.75
3
REINSTALL SALVAGED RAILING
$500.00
1 LUMP SUM
$500.00
1 LUMP SUM
$500.00
1 LUMP SUM
$500.0011
4
4" EXPOSED AGGREGATE CONCRETE WALK
$17.25
64 SF
$1,104.00
60 SF
$1,035.00
60 SF
$1,035.00
5
REMOVE CHAIN LINK FENCE PER INVOICE ON 8/3/11
$9.50
250 LF
$2,375.00
250 LF
$2,375.00
250 LF
$2,375.00
6
MISCELLANOUS CASTINGS PER INVOICE ON 8/3/11
$4,994.99
1 LUMP SUM
$4,994.99
1 LUMP SUM
$4,994.99
1 LUMP SUM
$4,994.99
7
LANDSCAPING REPAIRS AS OF 10/11/2011
$1,879.34
1 LUMP SUM
$1,879.34
1 LUMP SUM
$1,879.34
1 LUMP SUM
$1,879.34
8
IRRIGATION / LANDSCAPING INVOICE DATED 11/12/11
$2,198.05
1 LUMP SUM
$2,198.05
1 LUMP SUM
$2,198.05
1 LUMP SUM
$2,198.05
402 13th AVENUE N. SPRINKLER SYSTEMS LLC $158.72 1 1 LUMP SUM $158.72 1 LUMP SUM $158.72 1 LUMP SUM $158.72
346 14TH AVENUE N - AQUA CITY IRRIGATION $205.99 1 1 LUMP SUM $205.99 1 $205.99 1 LUMP SUM $205.99
LANDSCAPING ALLOWANCE TOTAL FOR TRACKING PURPOSES ONLY INCLUDED IN TOTAL PROJECT COST THRU ITEM NO. 56) $17,412.34 $17,412.34
TOTAL PROJECT COST (INCLUDING SUPPLEMENTAL AGREEMENTS) 1 $1,870,114.35 $1,758,003.79 $1,758,003.79
CITY OF HOPKINS
HENNEPIN COUNTY, MINNESOTA
RESOLUTION 2013-006
RESOLUTION ACCEPTING IMPROVEMENTS AND
AUTHORIZING FINAL PAYMENT
2011 STREET AND UTILITY IMPROVEMENTS
PROJECT 20 10- 10
WHEREAS, pursuant to a written contract signed with the City on May 17, 2011, Midwest
Asphalt Corporation, has satisfactorily completed construction of the 2011 Street and Utility Im-
provements Project, commonly known as City Project 2010-10, in accordance with such contract.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Hopkins,
Minnesota, that:
1. The work completed under said contract is hereby declared accepted and approved.
2. Order for final payment on such contract is hereby ordered, taking the contractor's receipt
in full.
Adopted by the City Council of Hopkins, Minnesota, this 5a' day of February, 2013.
Eugene J. Maxwell, Mayor
ATTEST:
Kristine A. Luedke, City Clerk