2024-2028 Capital Improvement PlanCAPITAL IMPROVEMENT PLAN 2024 - 2028 DATE: TO: FROM: November 21, 2023 Honorable Mayor and Members of the City Council Mike Mornson, City Manager SUBJECT: 2024-2028 CAPITAL IMPROVEMENT PLAN With this letter I respectfully submit the 2024-2028 Capital Improvement Plan. This five-year planning document represents the combined efforts of city staff, advisory commissions, residents and the City Council. The Capital Improvement Plan is a five-year forecast of project needs in the City of Hopkins. It is intended to alert the Council and residents to the major capital needs on the horizon. The first year of the plan becomes an adopted capital budget and relates almost completely to the operating budget that is approved on a yearly basis. The remaining four year represents an estimate of project needs and funding capabilities of the city. This plan does not include proposed equipment purchases. A document relating specifically to equipment replacement needs has been developed into a separate document. The Capital Improvement Plan is intended to serve as a planning tool and is therefore structured to present a meaningful, long-range perspective of the city’s capital programming needs. At the same time, sufficient projected detail is provided to enable those who review the information to make informed decisions on the programming of projects over the next several years. Please use the information provided to formulate plans, projects and questions. The Capital Improvement Plan can serve the community best by provoking thoughts and actions. This document was developed by the Finance Department with assistance of all city departments. I want to especially thank all those involved in the development of the Capital Improvement Plan and especially Chuck Autio, Public Works Director, Eric Klingbeil, City Engineer, Kersten Elverum, Planning and Economic Development Director, Ari Lenz, Assistant City Manager and Nick Bishop, Finance Director for their hard work and dedication. 1 2 Page City Manager's Message 1 Table of Contents 3 Introduction Introduction and Purpose 6 Program Descriptions Utilities Program 7 Transportation Program 8 Parks, Forestry, and Pavilion Program 10 General Public Buildings Program 11 Economic Development 13 Sources of Funding Sources of Funding 16 Funding Source Abreviations 19 Summary of Impacts on Major Funding Sources 22 Cash Flow Statements Park Capital Improvement Fund 26 Capital Improvement Fund 27 Permanent Improvement Revolving Fund (PIR)28 Municipal State Aid Fund 29 Water Utility Fund 30 Sewer Utility Fund 31 Storm Sewer Utiltiy Fund 32 Pavilion - Ice Arena Fund 33 Five-Year Project Summaries Department Summary 36 Projects by Department 37 Funding Source Summary 39 Projects by Funding Source 40 Project Descriptions & Narratives General Public Buildings 45 Parks & Recreation 75 Streets 83 Utilities 95 CAPITAL IMPROVEMENT PLAN 2024-2028 TABLE OF CONTENTS 3 4 Introduction 5 INTRODUCTION AND PURPOSE The Capital Improvement Plan is a flexible plan based upon long-range physical planning and financial projections, which schedules the major public improvements that may be incurred by the City over the next five years. Flexibility of the Capital Improvement Plan is established through annual review, and revision if necessary. The annual review assures that the program will become a continuing part of the budgetary process and that it will be consistent with changing demands as well as changing patterns in cost and financial resources. Funds are appropriated only for the first year of the program, which is then included in the annual budget. The Capital Improvement Plan serves as a tool for implementing certain aspects of the City's comprehensive plan; therefore, the program describes the overall objectives of City development, the relationship between projects with respect to timing and need, and the City's fiscal capabilities. The Capital Improvement Plan can help assure: 1. A systematic approach to planning and initiating capital projects affording the opportunity to plan the location, timing, and financing of needed public improvements; 2. The development of a realistic program of capital spending within the City's projected fiscal capability to finance such projects, avoiding sharp change in the tax levy or bonded indebtedness; 3. The coordination of public and private improvement projects permitting adequate time for design and engineering to eliminate duplication of effort and expense; 4. The expenditure of public funds that is compatible with the City's adopted Comprehensive Plan; 5. That the public is kept informed of the proposed future projects and expenditures; 6. That private investors are aware of the City's long-range development program so that they may guide their development in a way that is compatible with the City's program; 7. Aid in achieving federal and/or state participation by providing the necessary planning and lead time necessary for a successful application in addition to meeting prerequisites needed for certain federal and state grants. 6 PROGRAM DESCRIPTIONS In order to effectively plan for and manage the projects contained in a Capital Improvement Plan, it is necessary to group similar activities into "Program Categories". The City of Hopkins' activities are divided into four program categories which are 1) Utilities, 2) Transportation, 3) Parks, Forestry and Pavilion, and 4) General Public Buildings. The City also includes an outline of proposed expenditures for unscheduled projects. Program categories are explained in the following sections. UTILITIES PROGRAM Program Description: The Utilities Program includes the municipal water, municipal sanitary sewer, storm sewer and refuse systems. Program Goal: Provide reliable, efficient, and safe utility service to all parts of the City with a minimum of adverse effects on the environment. Subprograms: Water, sanitary sewer, storm sewer, and refuse service. I. Municipal Water System Subprogram (WA) A. Subprogram Goal: The goal of the Municipal Water System subprogram is to provide water in sufficient quantities at sufficient pressure, with a high degree of reliability and safety to all parts of the City so as to satisfy the normal demands of the general public for water while at the same time providing sufficient reserves in case of fire emergency or power outages. B. Objectives: 1. Water quality shall meet the purity standards of the Minnesota Department of Health. 2. Any hydrant on the system shall, under maximum condition, deliver no less than 500 gallons per minute with a residual pressure of 20 pounds per square inch. 3. The system shall be looped to provide maximum reliability. 4. The supply and storage system shall be designed and maintained to have maximum reliability. 7 II. Municipal Sanitary Sewer Subprogram (SA) A. Subprogram Goal: The goal of the Municipal Sanitary Sewer subprogram is to promote a healthful environment by collecting all sewage from existing and projected development in a sanitary and economic manner. B. Objectives: 1. Provide sewer lines of adequate size and grade to collect and transmit all discharge sewage. 2. Prevent sewage from overflowing into the natural environment. 3. Prevent sewage back-ups. 4. Encourage or promote connection of all generators of sewage to the Municipal system. 5. Meet the effluent and infiltration standards of the Metropolitan Waste Control Commission. III. Storm Sewer Subprogram (SS) A. Subprogram Goal: Manage and control surface and ground waters in order to protect the man-made and natural environment in a safe and efficient manner. B. Objectives: 1. Prevent flooding. 2. Prevent damage to property due to erosion. 3. Meet water quality standards established by the controlling regulatory law or authority. TRANSPORTATION PROGRAM Program Description: This program includes streets, walkways, traffic signs and signals, vehicular parking facilities, and street lighting. Program Goal: Provide for the safe and efficient movement of people and goods throughout the city. Subprograms: Streets, Walkways/Sidewalks, Signs/Signals, Parking Facilities, and Street Lights. 8 I. Streets Subprogram (ST) A. Subprogram Goal: The goal of the Streets subprogram is to provide safe, convenient, economic public streets to best facilitate the movement of vehicular traffic. B. Objectives: 1. Streets should be constructed with permanent surfaces, concrete curb and gutter, and with ancillary storm drainage, to standards established by the City. 2. Streets should be of a size and load capacity consistent with their functional classifications. 3. Timely major repair to preserve the basic capital investment in streets. II. Walkways/Sidewalks Subprogram (WS) A. Subprogram Goal: To provide a safe and convenient pedestrian system with incidental recreational benefits. III. Signs/Signals Subprogram (SI) A. Subprogram Goal: The goal of the Signs/Signals subprogram is to provide an efficient and orderly system of street and traffic signing so as to promote safe, convenient travel throughout the City. B. Objectives: 1. Signs and signals should be installed in conformity with the Minnesota Manual on Uniform Traffic Control Devices. 2. Periodic surveys and studies should be made to document the effectiveness of City signing patterns. IV. Parking Facilities Subprogram (PA) A. Subprogram Goal: To provide such supporting facilities as will promote maximum use of public parking spaces by employers, employees, customers, and visitors. B. Objectives: 1. Provide parking facilities for present and anticipated needs of the City of Hopkins. 9 V. Street Lights Subprogram (SL) A. Subprogram Goal: To provide a system of street lighting within the City that will promote safe and convenient vehicular and pedestrian travel on City Streets. B. Objectives: 1. To provide lighting at each street intersection within the City. 2. To provide mid-block street lighting in conformance with the City's street lighting policy, in order to provide equitable, cost efficient lighting. 3. To continually update the system so as to provide energy and cost efficient lighting. PARKS, FORESTRY AND PAVILION PROGRAM Program Description: This program includes community parks, neighborhood parks, open spaces, recreational structures and facilities. Program Goal: The goal of the Park and Recreation Program is to provide facilities for safe, stimulating, and comprehensive leisure time activities of Hopkins citizens. Subprograms: Neighborhood Facilities, Community Facilities I. Neighborhood Facilities Subprogram (NF) A. Subprogram Goals: To acquire ownership or use rights of park sites located to provide convenient walking access to all Hopkins citizens and to develop such sites to provide optimum recreational serviceability consistent with the preservation and enhancement of pleasing aesthetic qualities. B. Objectives: 1. Acquire property or use rights on those neighborhoods that do not have convenient walking access to neighborhood park facilities. 2. Develop neighborhood park facilities to meet the needs of various user groups. 3. Preserve and maintain existing structures and facilities in order to retain current service and safety levels. 4. Preserve and enhance the aesthetic qualities of neighborhood parks. 10 II. Community Facilities Subprogram (CF) A. Subprogram Goals: The goal of the Community Facilities subprogram is to develop, or acquire ownership or use rights of sites which serve the entire City and to provide facilities that serve community-wide needs. B. Objectives: 1. Acquire sites that have valuable and unique natural characteristics to preserve irreplaceable community resources. 2. Preserve by acquisition, gift, or other arrangement properties that have valuable historic-cultural qualities. 3. Preserve and maintain existing structures and facilities in order to retain current service and safety levels. 4. Construct or acquire structures and facilities necessary to meet the changing needs of the community. GENERAL PUBLIC BUILDINGS PROGRAM Program Description: The General Public Buildings Program includes all municipal buildings except those provided for in the Utility and Park Facilities Program. Program Goal: Provide buildings that are adequate and convenient for the efficient accommodation of City functions. Subprograms: Administrative Offices, Maintenance Facilities, Fire Facilities, Community Center. I. Administrative Offices Subprogram (AO) A. Subprogram Goal: The goal of the Administrative Offices subprogram is to provide facilities for the efficient and safe conduct of legislative and administrative functions of the City. B. Objectives: 1. Maintain current facilities in a state of good repair so as to maximize cost effectiveness and avoid costly repair. 2. Upgrade facilities as necessary to provide for the efficient, safe, and effective provision of the City services. 11 II. Maintenance Facilities Subprogram (MF) A. Subprogram Goal: The goal of the Maintenance Facilities subprogram is to provide facilities for the efficient and safe conduct of City maintenance functions. B. Objectives: 1. Maintain current facilities in a state of good repair so as to maximize cost effectiveness and avoid costly repair. 2. Upgrade facilities as necessary to provide for the efficient, safe, and effective provision of City services. III. Fire Facilities Subprogram (FF) A. Subprogram Goal: To provide a fire station, or stations, for storage of Fire Department equipment and for the training and meetings of volunteer fire fighters to provide prompt and efficient protection to life and property. B. Objectives: 1. Provide a maximum four-minute daytime and three-minute nighttime response to all points within the City. 2. Meet objective 1 through the use of volunteers. IV. Community Center Subprogram (CC) A. Subprogram Goal: To provide a community facility, or facilities, which meet the social, recreational, and cultural needs of all citizens, particularly senior citizens. B. Objectives: 1. Maintain current facilities in a state of good repair so as to maximize cost effectiveness and avoid costly repairs. 2. Construct or acquire structures and facilities necessary to meet the changing needs of the City. 3. Upgrade facilities as necessary to provide for efficient, safe, and effective provision of City services. 12 ECONOMIC DEVELOPMENT PROGRAM Program Description: This program includes redevelopment projects that have been identified through adopted plans and goals of the City of Hopkins. Program Goal: To facilitate the redevelopment of key sites in order to achieve the state objectives of the project. Objectives: 1.Elimination of blight or blighting conditions 2.Creation of jobs 3.Increase property value(s) 4.Catalyst of additional redevelopment 5.Environmental clean-up 6.Increase transit-oriented development around LRT stations 13 14 Sources of Funding 15 SOURCES OF FUNDING In order to fund the anticipated Capital Improvements, the City must draw upon a variety of sources. Many of these sources have a specific or "dedicated" purpose (i.e., the water utility fund will finance water main installation but not a street overlay). Therefore, it is important to identify the uses and limitations of the various revenue sources. CURRENT REVENUES - GENERAL FUND (CR) This represents funding from current year revenue collections in the General Fund that support operations and capital outlay expenditures. Revenue sources include property tax levies, state aid payments, and various permit and license fees. This source of funding is generally used only for operations and small capital purchases. GENERAL FUND RESERVES (GR) Reserves of the general fund are the funds remaining after subtracting cash flow and emergency amounts from the City's cash balance, sometimes referred to as "fund balance". The use of General Fund Reserves is not recommended for Capital Improvements without significant staff and Council review. COMMUNICATION (formerly Cable TV) FUND (CT) This funding source consists of franchise fees received from the local Cable TV company, in excess of the amounts earmarked for the access programming and commission budgets. Expenditures are limited to cable-related facilities, or must have a cable related purpose. ECONOMIC DEVELOPMENT FUND (ED) This funding source was established by the Housing and Redevelopment Authority (HRA) and the City of Hopkins, to provide funding for the purpose of promoting development and redevelopment within the City. The Economic Development fund is a revolving fund administered by the HRA, intended to provide an ongoing funding source used to reduce or extend the long term debt involved with development and redevelopment activities. The HRA reviews all proposed uses of this fund on an individual basis. GRANT-IN-AID (GA) This is aid received from either the Federal or State government. In many cases, grants are made on matching basis, which means the City shares a portion of the costs of the project being funded. 16 MUNICIPAL STATE AID STREETS (MS) This funding source represents funds received from the State of Minnesota to support construction and maintenance of State Aid classified municipal streets. State law defines the types and limits of State Aid Streets expenditures. PERMANENT IMPROVEMENT REVOLVING/GENERAL OBLIGATION BONDS (PI) Improvements with a life of several years may be financed from the proceeds of a General Obligation Bond Issue. Law limits the total debt that can be incurred under this method of financing. With some exception, General Obligation Bonds are generally subject to a referendum process. Examples of projects, which may not require a referendum, are those financed through the use of special assessments where at least 20 percent of the project cost is assessed to the benefiting property owners. The remaining portion not assessed can be financed through general obligation bonds repaid by a tax levy. PRIVATE SECTOR FUNDING (PF) This funding source consists primarily of payments made by developers for the purchase of land, the installation of water, sewer, or streets or other related expenditures. It can also refer to donations made to the City by individuals or groups. OTHER GOVERNMENTAL UNITS (GU) These are funds received from Hennepin County, adjacent communities, etc. for projects that also benefit a jurisdiction other than the City of Hopkins. REVENUE BONDS (RB) These are bonds issued for improvements made for specific revenue producing facility or operation. The debt incurred is repaid from the revenue generated by the facility. If the revenue generated is insufficient, then the difference becomes an annual obligation of the taxpayers and becomes an additional tax levy. These are generally not subject to referendum. REAL ESTATE SALES FUND (RE) This funding source consists primarily of funds built up from the sale of City owned property. To date, the fund has been used for building improvements. Because the sale of both general City property and park/recreation property are accumulated into this fund, earmarking a portion for recreational purposes may be justified. 17 SPECIAL ASSESSMENT (SA) A number of projects may be realistically financed using Special Assessment to pay the ultimate cost. Almost any project can potentially be financed using the assessment process. In each case it is necessary to make a determination that the assessed property will benefit by the amount of the assessment. The cost of street reconstruction is shared by the property owner and the City. Special assessments to individual properties are capped per city policy. Concurrent improvement costs to the utility systems are assumed by the respective utility funds. TAX INCREMENT FINANCING (TF) This funding source results from the tax value of new development that is "incrementally" greater than the existing tax value. Typically, bonds are sold based on the assumption that the higher tax receipts will retire the bonds. However, the use of TIF funds through a "pay as you go" method has become more common. This type of funding can be used for public improvements within a redevelopment district to support the goals of redevelopment, specifically the elimination of blighted conditions. Approval of the Hopkins HRA should be anticipated prior to the commitment of these funds. State law strictly regulates the use of these funds. WATER FUNDS (WF) Water funds consist of revenue generated from the sale of water. The cost of operations plus system (capital) improvements determines the ultimate charge levied for the service provided. SANITARY SEWER FUNDS (SF) Sanitary sewer funds consist of revenue generated from charges made for sewage disposal. The cost of operations plus system (capital) improvements determines the ultimate charge levied for the service provided. STORM SEWER UTILITY REVENUES (SU) Storm sewer funds consist of revenue generated by charging storm water drainage fee to parcels of land for the availability and use of municipal storm sewer facilities. Expenditures from this funding source are related to drainage facilities. PAVILION FUND (PA) Pavilion Funds consist of revenues generated from rental fees collected from users of the Pavilion. These funds are utilized to pay for operating, and capital expenditures. 18 Funding Sources Communication (formerly Cable TV) Fund CT Current Revenues – General Fund CR General Fund Reserves GR Economic Development Fund ED Grant-In-Aid GA Housing and Redevelopment Authority HRA Municipal State-Aid Streets MS Other Government Units GU Park Dedication Fund PDF Pavilion Fund PA Permanent Improvement Revolving/General Obligation Bonds PI Private Sector Funds PF Real Estate Sales Fund RE Revenue Bonds RB Sanitary Sewer Fund SF Special Assessment SA Storm Sewer Fund SU Tax Increment Financing TF Water Fund WF 19 20 Summary of Impacts on Major Funding Sources 21 SUMMARY OF PROJECT IMPACTS ON MAJOR FUNDING SOURCES CURRENT REVENUES/GENERAL FUND RESERVES Expenditures for 2024 are budgeted at an increase of 7.18% over the 2023 budget. The 2024 budget has no levy limits, and the City will receive approximately $1.08 million in LGA. The tax levy is the major source of revenues (81%) for the General Fund and therefore presents a challenge when levy limits are in place. Unassigned fund balance in the General Fund totals $8,475,285 at the end of 2022 and is projected to decrease by $400,000 in 2024 based on a budgeted use of surplus funds. The State Auditor’s Office recommends no less than five month of operating expenditures in reserves. For 2023 five months of expenditures would total $7,161,850 or 41.7%. On January 1, 2023, the unassigned fund balance was at 49.3% of budgeted expenditures. PERMANENT IMPROVEMENT REVOLVING FUND, (P.I.R.) - G.O. DEBT Funding from bonds is used to reimburse the P.I.R. fund for public improvement projects, which have been previously expended. The debt is funded by special assessment collections and city tax levies over a ten to fifteen year period. Bonds totaling $3,975,000 were sold in 2023 to fund the 2023 street improvement project. The next bond sale is scheduled for 2024 and will be for the 2024 street improvement project. These bonds are expected to total approximately $4,258,000. The P.I.R. fund has completed substantial projects over the last five years. The pace is expected to continue through 2030. Projects scheduled for 2024-2028 will require bonding. Projects scheduled for 2024 include the Central Avenues street reconstruction project, pedestrian and bicycle access improvements, along with street overlay, street sign management programs and street lighting upgrades. The funding is provided for these projects by special assessments, PIR/Bonding and general fund transfers. MUNICIPAL STATE AID FUND Funding for municipal state aid road projects comes from state MSA funding and is drawn down as projects are done. State funding is not sufficient for current planned projects as the City has been aggressive in doing MSA projects. In the queue for reimbursement is a request for is the Shady Oak project. In late 2014 we received an advance on the Shady Oak project which essentially cleared up our receivable backlog for Excelsior Blvd and Minnetonka Mills Road. This leaves Shady Oak Road as the only project in the funding queue. Currently no MSA projects are scheduled. 22 CAPITAL IMPROVEMENT FUND The Capital Improvement Fund received only tax levy support from 2005 through 2018. Gas and electric franchise fees were increased beginning in 2019, to support the capital improvement fund. The franchise fees are expected to generate $361,500 annually for the fund. Projects scheduled for 2024 include replacement of HVAC systems, roof replacements, floor coverings and building automation system upgrades. PARK IMPROVEMENT FUND The source of funding for this fund is development fees charged to developers for park development, in addition to franchise fees from gas and electric services. The franchise fees were increased for 2024 and should generate $355,000 to the fund for much needed park projects. The City is seeing an increased interest in development with $1,700,000 of dedication fees projected to be received in 2025. Projects scheduled for 2024 are court improvements and a Central Park Master plan. WATER FUND Increasing consumption charges and bond proceeds in 2024 provide the funding needed for projects scheduled for 2024. Bonds will need to be sold each year thereafter in which there are water projects associated with the residential street improvement program. Projects planned for 2024 total $2,900,000 and include water main improvements done in conjunction with the Central Avenues street reconstruction project, water meter replacements, lift station rehabilitation and SCADA fiber. SANITARY SEWER FUND Increasing consumption charges and bond proceeds in 2024 provide the funding needed for projects scheduled for 2024. Bonds will need to be sold each year thereafter in which there are sanitary sewer projects associated with the residential street improvement program. Projects planned for 2024 total $2,565,000 and include water main improvements done in conjunction with the Central Avenues street reconstruction project, water meter replacements, lift station rehabilitation and SCADA fiber. STORM SEWER FUND Bonds will be sold in 2024 for the 2024 storm water management project. These bonds issues along with current revenues should provide the needed funding for scheduled projects. Bonds will need to be sold each year thereafter in which there are storm sewer projects associated with the residential street improvement program. Projects planned for 2024 total $447,000 and include storm sewer improvements done in conjunction with the West Central Avenues street reconstruction project. The most recent rate increase pursuant to the 2007 Utility Master Plan was done in 2009. This rate increase is expected to support the storm sewer system well into the future and currently no additional rates increases are proposed. 23 PAVILION FUND This facility completed a significant upgrade project in 2018, with a total project cost of approximately $5,700,000. The new expanded facility has a new refrigeration system and was expanded to better meet the needs of the community. The project received contributions from the Park Improvement Fund along with outside organizations. A bond was issued for the remaining costs of approximately $3,200,000. The fund will continue to receive tax levy support in 2023 to pay ongoing debt service costs and capital projects. Projects scheduled for 2024 include replacement of flooring, water heaters and exterior doors. 24 Cash Flow Statements 25 City of Hopkins Park Capital Improvements Fund (301) PROJECTED BUDGET BUDGET BUDGET BUDGET BUDGET 2023 2024 2025 2026 2027 2028 Working Capital Begin Year 912,656 1,046,124 763,106 2,504,137 2,615,878 2,808,737 Revenues Franchise Fees 305,000 355,000 355,000 355,000 355,000 305,000 Dedication Fees - - 1,700,000 - - - Interest earnings 8,468 26,682 7,631 25,041 26,159 28,087 Hennepin County Grants - - - - - - Donations - - - - - - Transfer In - - - - - - Bond Proceeds - - - - - - Total Revenues 313,468 381,682 2,062,631 380,041 381,159 333,087 Expenditures Current 15,000 15,000 15,000 15,000 15,000 15,000 Capital Projects 5,000 479,700 136,600 83,300 3,300 3,300 Bond Payment Contribution (2015)10,000 10,000 10,000 10,000 10,000 10,000 Bond Payment Contribution (2016)100,000 110,000 110,000 110,000 110,000 110,000 Bond Payment Contribution (2017)50,000 50,000 50,000 50,000 50,000 50,000 Total Expenditures 180,000 664,700 321,600 268,300 188,300 188,300 Working Capital Ending Balance 1,046,124 763,106 2,504,137 2,615,878 2,808,737 2,953,524 (Unrestricted Net Position) 26 City of Hopkins Capital Improvements Fund (305) PROJECTED BUDGET BUDGET BUDGET BUDGET BUDGET 2023 2024 2025 2026 2027 2028 Working Capital Begin Year 101,504 531,644 272,004 459,044 230,003 171,733 Revenues from charges Tax Levy - - 828,000 800,000 800,000 800,000 Federal Grants - - - - - - Interest earnings 990 5,360 1,040 459 230 172 Franchise Fees 361,500 361,500 361,500 361,500 361,500 361,500 Transfer In 427,650 - - - - - Total Revenues 790,140 366,860 1,190,540 1,161,959 1,161,730 1,161,672 Expenditures Capital Projects - 266,500 643,500 1,031,000 860,000 850,000 City Hall Debt Service 360,000 360,000 360,000 360,000 360,000 360,000 Total Expenditures 360,000 626,500 1,003,500 1,391,000 1,220,000 1,210,000 Working Capital Ending Balance 531,644 272,004 459,044 230,003 171,733 123,405 (Unrestricted Net Position) 27 City of Hopkins Permanent Improving Revolving Fund (501) PROJECTED BUDGET BUDGET BUDGET BUDGET BUDGET 2023 2024 2025 2026 2027 2028 Working Capital Begin Year 994,413 1,499,357 1,019,351 997,545 1,036,020 1,020,380 Revenues Tax Levy - - 510,000 260,000 275,000 110,000 Special Assessments (Prepaid)210,000 162,000 120,000 120,000 170,000 130,000 Investments 9,944 14,994 10,194 9,975 10,360 10,204 Bond Proceeds 3,975,000 4,258,000 3,995,000 4,100,000 6,250,000 5,425,000 Transfer In 290,000 - - Total Revenues 4,484,944 4,434,994 4,635,194 4,489,975 6,705,360 5,675,204 Expenditures Residential Street Improvements 3,220,000 4,420,000 3,640,000 3,640,000 5,250,000 4,930,000 Central Business District Lighting Upgrades 100,000 - 40,000 - - - City Street Lighting Upgrades 190,000 - 200,000 90,000 225,000 60,000 Pedestrian & Bicycle Access Improvements 25,000 25,000 100,000 27,500 30,000 32,500 Street Overlay Improvements 425,000 450,000 475,000 500,000 550,000 575,000 Street Sign Management 20,000 20,000 22,000 24,000 26,000 26,000 Mainstreet Banner Pole Installation - - 130,000 120,000 - - Excelsior Blvd. Fencing - - 50,000 50,000 50,000 50,000 Minnetonka Mills Signal Replacement - - - - 590,000 - Total Expenditures 3,980,000 4,915,000 4,657,000 4,451,500 6,721,000 5,673,500 Working Capital Ending Balance 1,499,357 1,019,351 997,545 1,036,020 1,020,380 1,022,084 (Unrestricted Net Position) 28 City of Hopkins Municipal State Aid Fund (302) PROJECTED BUDGET BUDGET BUDGET BUDGET 2023 2024 2025 2026 2027 Working Capital Begin Year 1,059,110 1,083,053 1,789,718 2,524,324 2,524,324 Revenues State MSA Funds, projects - 695,834 716,709 738,210 760,356 Interest Earnings 23,943 10,831 17,897 25,243 25,243 Total Revenues 23,943 706,665 734,606 Expenditures CIP State Aid Projects - - - - - Total Expenditures - - - - - Working Capital Ending Balance 1,083,053 1,789,718 2,524,324 2,524,324 2,524,324 (Unrestricted Net Position) 29 Water Fund (703) - Working Capital Projection PROJECTED BUDGET BUDGET BUDGET BUDGET BUDGET 2023 2024 2025 2026 2027 2028 Working Capital Begin Year 1,124,041 1,682,948 1,346,773 1,092,997 999,349 1,169,186 Revenues Operating Revenues 2,522,686 2,747,400 2,994,666 3,264,186 3,557,963 3,878,179 Other 123,152 145,000 147,900 150,858 153,875 156,953 Federal Grants Bond Proceeds - Capital 1,359,000 2,900,000 1,400,000 1,475,000 7,150,000 - Bond Proceeds - Refunding - - - - - - Total Revenues 4,004,838 5,792,400 4,542,566 4,890,044 10,861,838 4,035,132 Expenditures Operating Expenditures 1,701,072 1,995,870 2,055,746 2,117,418 2,180,941 2,246,369 Interest/Fiscal Agent Expense 260,816 294,798 287,236 238,681 193,019 169,130 Capital Outlay 839,167 2,900,000 1,390,000 1,478,000 7,140,000 198,000 Bond Payments 485,450 699,600 806,269 892,501 920,950 943,850 Transfer Out - Bond Payments 159,426 238,307 257,091 257,091 257,091 257,091 Total Expenses 3,445,931 6,128,575 4,796,342 4,983,691 10,692,001 3,814,440 Working Capital Ending Balance 1,682,948 1,346,773 1,092,997 999,349 1,169,186 1,389,878 (Unrestricted Net Position) 30 City of Hopkins Sewer Fund (707) - Working Capital Projection PROJECTED BUDGET BUDGET BUDGET BUDGET BUDGET 2023 2024 2025 2026 2027 2028 Working Capital Begin Year 1,492,848 2,086,423 2,089,195 2,043,725 1,980,093 1,926,837 Revenues Operating Revenues 3,323,407 3,600,000 3,708,000 3,819,240 3,933,817 4,051,832 Other 86,857 15,000 15,300 15,606 15,918 16,236 Interest - 20,000 20,892 20,437 19,801 19,268 Bond Proceeds - Capital 1,224,000 2,565,000 1,355,000 1,185,000 2,025,000 1,650,000 Total Revenues 4,634,264 6,200,000 5,099,192 5,040,283 5,994,536 5,737,337 Expenditures Operating Expenditures 2,537,378 2,839,706 2,924,897 3,012,644 3,103,023 3,196,114 Interest/Fiscal Agent Expense 108,974 149,768 128,076 109,047 95,215 82,961 Capital Outlay 884,965 2,565,000 1,355,000 1,183,000 2,035,000 1,650,000 Bond Payments 377,540 398,170 492,105 554,640 569,970 578,450 Transfer Out - Bond Payments 131,832 244,584 244,584 244,584 244,584 244,584 Total Expenses 4,040,689 6,197,228 5,144,662 5,103,915 6,047,792 5,752,109 Working Capital Ending Balance 2,086,423 2,089,195 2,043,725 1,980,093 1,926,837 1,912,065 (Unrestricted Net Position) 31 City of Hopkins Storm Sewer (740) Fund - Working Capital Projection PROJECTED BUDGET BUDGET BUDGET BUDGET BUDGET 2023 2024 2025 2026 2027 2028 Working Capital Begin Year 1,273,734 1,742,709 1,812,717 1,809,046 1,756,950 1,709,422 Revenues Operating Revenues 796,135 779,332 779,332 779,332 779,332 779,332 Other 5,897 6,000 6,000 6,000 6,000 6,000 Interest - 25,000 18,127 18,090 17,569 17,094 Bond Proceeds - Capital 767,000 450,000 275,000 290,000 930,000 570,000 Total Revenues 1,569,032 1,260,332 1,078,459 1,093,422 1,732,901 1,372,426 Expenditures Operating Expenditures 143,711 188,457 194,111 199,934 205,932 212,110 Interest/Fiscal Agent Expense 68,836 97,829 98,586 76,551 55,609 47,170 Capital Outlay - Construction 419,996 447,000 273,000 292,000 930,000 572,500 Bond Payments 312,010 242,230 301,625 362,226 374,080 381,700 Transfer Out - Bond Payments 155,504 214,808 214,808 214,808 214,808 214,808 Total Expenses 1,100,057 1,190,324 1,082,130 1,145,519 1,780,429 1,428,288 Working Capital Ending Balance 1,742,709 1,812,717 1,809,046 1,756,950 1,709,422 1,653,560 (Unrestricted Net Position) 32 City of Hopkins Pavilion Fund (747) - Working Capital Projection PROJECTED BUDGET BUDGET BUDGET BUDGET BUDGET 2023 2024 2025 2026 2027 2028 Working Capital Begin Year 98,706 (41,767) (18,017) 3,236 24,094 44,660 Revenues Property Taxes 340,000 440,000 569,000 340,000 415,000 340,000 Federal Grants - - Operating Revenues 509,975 471,500 485,645 500,214 515,220 530,677 Other 118 7,500 7,500 7,500 7,500 7,500 Total Revenues 850,093 919,000 1,062,145 847,714 937,720 878,177 Expenditures Operating Expenditures 589,880 523,900 539,617 555,806 572,480 589,654 Interest/Fiscal Agent Expense 76,438 73,350 67,275 61,050 54,675 48,075 Capital Outlay - Construction 129,248 98,000 229,000 - 75,000 - Bond Payments 195,000 200,000 205,000 210,000 215,000 225,000 Total Expenses 990,566 895,250 1,040,892 826,856 917,155 862,729 Working Capital Ending Balance (41,767) (18,017) 3,236 24,094 44,660 60,108 (Unrestricted Net Position) 33 34 Five Year Project Summaries 35 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP DEPARTMENT SUMMARY 2024 2028thru Total20242025202620272028Department City Hall Administration 1,068,000140,000 18,000 60,000 850,000 Comm Svcs - Activity Center 438,00039,500 398,500 Comm Svcs - Arts Center 1,003,500110,500 85,000 780,000 28,000 Fire 642,00092,000 550,000 Pavilion 402,00098,000 229,000 75,000 Public Works: Bldg/Equip Serv 2,000,000135,000 105,000 160,000 1,600,000 Public Works: Parks 660,000450,000 130,000 80,000 Public Works: Streets/Traffic 43,386,0007,915,000 7,182,000 6,976,500 10,971,000 10,341,500 Public Works: Utilities 8,936,5002,912,000 493,000 374,000 5,105,000 52,500 Recreation 140,00090,000 20,000 10,000 10,000 10,000 11,842,000 8,782,500 8,948,500 17,849,000 11,254,000 58,676,000TOTAL Wednesday, November 15, 202336 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP PROJECTS BY DEPARTMENT 2024 2028thru Total20242025202620272028DepartmentProject #Priority City Hall Administration 09-CIP-CH032 18,00018,000Council Chambers HVAC Unit n/a 09-CIP-CH035 60,00060,000City Hall AC Rooftop Units n/a 23-CIP-CH038 990,000140,000 850,000City Hall/Police Station - Roof Replacement n/a 1,068,000140,000 18,000 60,000 850,000City Hall Administration Total Comm Svcs - Activity Center 22-CIP-AC052 120,000120,000Activity Center - Tuckpointing & Repair of Brick 2 23-CIP-AC053 250,000250,000Activity Center - Roof Replacement & Flashing n/a 23-CIP-AC054 39,50039,500Floor Covering - Entry, Commons and Dining Area n/a 23-CIP-AC055 10,00010,000Activity Center - Countertops n/a 23-CIP-AC056 18,50018,500Activity Center - Main Interior Door Replacement n/a 438,00039,500 398,500Comm Svcs - Activity Center Total Comm Svcs - Arts Center 14-CIP-AR003 28,00028,000Arts Center - Paint Theatre 2 19-CIP-AR002 50,00025,000 25,000Arts Center - Outdoor Signage/lighting 2 19-CIP-AR005 102,50012,500 60,000 30,000 0Arts Center - Access/Lockdown System 2 19-CIP-AR007 750,000750,000Arts Center - Roof Replacement 2 23-CIP-AR004 50,50050,500Arts Center - Exterior Door Repairs n/a 23-CIP-AR005 22,50022,500Arts Center - Security Cameras 1 1,003,500110,500 85,000 780,000 28,000Comm Svcs - Arts Center Total Fire 08-CIP-B121 92,00092,000Fire Station: Replace 25 Ton AHU n/a 08-CIP-B125 550,000550,000Fire - Replace Roof n/a 642,00092,000 550,000Fire Total Pavilion 20-CIP-PV333 25,00025,000Pavilion - Mezzanine Flooring Replacement 3 20-CIP-PV334 115,000115,000Pavilion - Arena Exit Door Replacement 3 22-CIP-PV335 50,00050,000Pavilion - Water Heater Replacement n/a 23-CIP-PV336 100,000100,000Pavilion - Roof Replacement n/a 23-CIP-PV337 75,00075,000Pavilion - Bleacher Heating Replacement 3 23-CIP-PV338 23,00023,000Pavilion - Door Replacement 3 23-CIP-PV339 14,00014,000Pavilion - Warming House Window Blinds 3 402,00098,000 229,000 75,000Pavilion Total Public Works: Bldg/Equip Serv 08-CIP-B022 1,600,0001,600,000Public Works - Replace Roofing n/a 08-CIP-B023 90,00090,000Public Works - Replace Overhead Doors n/a 21-CIP-B101 105,000105,000907 Mainstreet (HHS) Windows & Front/Back Door 5 Wednesday, November 15, 202337 Total20242025202620272028DepartmentProject #Priority 22-CIP-B102 70,00070,000Undercarriage Wash System 3 23-CIP-B103 60,00060,000Building Automation System-Replacements & Upgrades 2 23-CIP-B104 75,00075,000Parking Ramp Roof Replacement n/a 2,000,000135,000 105,000 160,000 1,600,000Public Works: Bldg/Equip Serv Total Public Works: Parks 13-CIP-P044 230,000230,000Improve Courts: Oakes, Cottageville & Interlachen 2 21-CIP-P073 70,00070,000Repair Valley ParkVolleytball Court 1 21-CIP-P074 130,000130,000Repair Burnes Park Tennis Courts n/a 21-CIP-P075 80,00080,000Repair Play Courts- Elmo & Park Valley n/a 23-CIP-P076 150,000150,000Central Park Master Plan n/a 660,000450,000 130,000 80,000Public Works: Parks Total Public Works: Streets/Traffic 01-CIP-S101 36,538,0007,420,000 6,165,000 6,165,000 9,490,000 7,298,000Residential Street Improvements and Utilities n/a 01-CIP-S104 2,300,0002,300,000County Road 3 n/a 13-CIP-S040 215,00025,000 100,000 27,500 30,000 32,500Pedestrian & Bicycle Access Improvements n/a 16-CIP-S041 2,550,000450,000 475,000 500,000 550,000 575,000Street Rehabilitation Improvements n/a 16-CIP-S042 118,00020,000 22,000 24,000 26,000 26,000Street Sign Management n/a 20-CIP-S001 40,00040,000Central Business District Lighting Upgrades n/a 20-CIP-S002 575,000200,000 90,000 225,000 60,000City Street Lighting Upgrades n/a 20-CIP-S005 600,000600,000Minnetonka Mills/5th St N Signal Replacement 5 23-CIP-S007 250,000130,000 120,000Mainstreet Banner Pole Installation n/a 23-CIP-S008 200,00050,000 50,000 50,000 50,000Excelsrior Blvd. Fencing n/a 43,386,0007,915,000 7,182,000 6,976,500 10,971,000 10,341,500Public Works: Streets/Traffic Total Public Works: Utilities 01-CIP-U002 146,50027,000 28,000 29,000 30,000 32,500Storm Drainage System Maintenance - Alley Repairs n/a 18-CIP-U016 275,00060,000 65,000 75,000 75,000Sewer Lining 2 19-CIP-U017 5,000,0005,000,000Trunk Water Main Rehabilitation 2 23-CIP-U018 290,000270,000 20,000Water Treatment Plant - Roof Replacement n/a 23-CIP-U019 25,00025,000Well #5 Roof Replacement 1 23-CIP-U020 2,200,0002,200,000Citywide Meter Replacement n/a 23-CIP-U021 250,000250,000Lift Station No. 2 n/a 23-CIP-U022 750,000350,000 400,000SCADA Fiber Project n/a 8,936,5002,912,000 493,000 374,000 5,105,000 52,500Public Works: Utilities Total Recreation 16-CIP-R003 140,00090,000 20,000 10,000 10,000 10,000Shady Oak Beach Improvements 3 140,00090,000 20,000 10,000 10,000 10,000Recreation Total GRAND TOTAL 58,676,00011,842,000 8,782,500 8,948,500 17,849,000 11,254,000 Wednesday, November 15, 202338 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP FUNDING SOURCE SUMMARY 2024 thru 2028 TotalSource20242025202620272028 AC - Arts Center Fund 628,500110,500 85,000 405,000 28,000 CI - Capital Improvement Fund 3,651,000266,500 643,500 1,031,000 860,000 850,000 GU - Other Governmental Units 1,693,80060,300 13,400 6,700 6,700 1,606,700 MS - Municipal State Aid Streets 700,000700,000 PA - Pavilion Fund 402,00098,000 229,000 75,000 PDF- Park Dedication Fund 706,200479,700 136,600 83,300 3,300 3,300 PI - PIR/General Obligation Bonds 22,908,0004,105,000 4,057,000 3,851,500 5,871,000 5,023,500 RF - Refuse Fund 68,00018,000 50,000 SA - Special Assessment 3,510,000810,000 600,000 600,000 850,000 650,000 SF - Sanitary Sewer Fund 8,788,0002,565,000 1,355,000 1,183,000 2,035,000 1,650,000 SU - Storm Sewer Fund 2,514,500447,000 273,000 292,000 930,000 572,500 WF - Water Fund 13,106,0002,900,000 1,390,000 1,478,000 7,140,000 198,000 11,842,000 8,782,500 8,948,500 17,849,000 11,254,000 58,676,000GRAND TOTAL Wednesday, November 15, 2023 39 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP PROJECTS BY FUNDING SOURCE 2024 2028thru TotalSourceProject #Priority 2024 2025 2026 2027 2028 AC - Arts Center Fund 14-CIP-AR003 28,00028,000Arts Center - Paint Theatre 2 19-CIP-AR002 50,00025,000 25,000Arts Center - Outdoor Signage/lighting 2 19-CIP-AR005 102,50012,500 60,000 30,000 0Arts Center - Access/Lockdown System 2 19-CIP-AR007 375,000375,000Arts Center - Roof Replacement 2 23-CIP-AR004 50,50050,500Arts Center - Exterior Door Repairs n/a 23-CIP-AR005 22,50022,500Arts Center - Security Cameras 1 628,500110,500 85,000 405,000 28,000AC - Arts Center Fund Total CI - Capital Improvement Fund 08-CIP-B022 800,000800,000Public Works - Replace Roofing n/a 08-CIP-B023 18,00018,000Public Works - Replace Overhead Doors n/a 08-CIP-B121 92,00092,000Fire Station: Replace 25 Ton AHU n/a 08-CIP-B125 550,000550,000Fire - Replace Roof n/a 09-CIP-CH032 18,00018,000Council Chambers HVAC Unit n/a 09-CIP-CH035 60,00060,000City Hall AC Rooftop Units n/a 19-CIP-AR007 375,000375,000Arts Center - Roof Replacement 2 21-CIP-B101 105,000105,000907 Mainstreet (HHS) Windows & Front/Back Door 5 22-CIP-AC052 120,000120,000Activity Center - Tuckpointing & Repair of Brick 2 22-CIP-B102 70,00070,000Undercarriage Wash System 3 23-CIP-AC053 250,000250,000Activity Center - Roof Replacement & Flashing n/a 23-CIP-AC054 39,50039,500Floor Covering - Entry, Commons and Dining Area n/a 23-CIP-AC055 10,00010,000Activity Center - Countertops n/a 23-CIP-AC056 18,50018,500Activity Center - Main Interior Door Replacement n/a 23-CIP-B103 60,00060,000Building Automation System-Replacements & Upgrades 2 23-CIP-B104 75,00075,000Parking Ramp Roof Replacement n/a 23-CIP-CH038 990,000140,000 850,000City Hall/Police Station - Roof Replacement n/a 3,651,000266,500 643,500 1,031,000 860,000 850,000CI - Capital Improvement Fund Total GU - Other Governmental Units 01-CIP-S104 1,600,0001,600,000County Road 3 n/a 16-CIP-R003 93,80060,300 13,400 6,700 6,700 6,700Shady Oak Beach Improvements 3 1,693,80060,300 13,400 6,700 6,700 1,606,700GU - Other Governmental Units Total MS - Municipal State Aid Streets 01-CIP-S104 700,000700,000County Road 3 n/a 700,000700,000MS - Municipal State Aid Streets Total PA - Pavilion Fund 20-CIP-PV333 25,00025,000Pavilion - Mezzanine Flooring Replacement 3 Wednesday, November 15, 2023 40 TotalSourceProject #Priority 2024 2025 2026 2027 2028 20-CIP-PV334 115,000115,000Pavilion - Arena Exit Door Replacement 3 22-CIP-PV335 50,00050,000Pavilion - Water Heater Replacement n/a 23-CIP-PV336 100,000100,000Pavilion - Roof Replacement n/a 23-CIP-PV337 75,00075,000Pavilion - Bleacher Heating Replacement 3 23-CIP-PV338 23,00023,000Pavilion - Door Replacement 3 23-CIP-PV339 14,00014,000Pavilion - Warming House Window Blinds 3 402,00098,000 229,000 75,000PA - Pavilion Fund Total PDF- Park Dedication Fund 13-CIP-P044 230,000230,000Improve Courts: Oakes, Cottageville & Interlachen 2 16-CIP-R003 46,20029,700 6,600 3,300 3,300 3,300Shady Oak Beach Improvements 3 21-CIP-P073 70,00070,000Repair Valley ParkVolleytball Court 1 21-CIP-P074 130,000130,000Repair Burnes Park Tennis Courts n/a 21-CIP-P075 80,00080,000Repair Play Courts- Elmo & Park Valley n/a 23-CIP-P076 150,000150,000Central Park Master Plan n/a 706,200479,700 136,600 83,300 3,300 3,300PDF- Park Dedication Fund Total PI - PIR/General Obligation Bonds 01-CIP-S101 18,370,0003,610,000 3,040,000 3,040,000 4,400,000 4,280,000Residential Street Improvements and Utilities n/a 13-CIP-S040 215,00025,000 100,000 27,500 30,000 32,500Pedestrian & Bicycle Access Improvements n/a 16-CIP-S041 2,550,000450,000 475,000 500,000 550,000 575,000Street Rehabilitation Improvements n/a 16-CIP-S042 118,00020,000 22,000 24,000 26,000 26,000Street Sign Management n/a 20-CIP-S001 40,00040,000Central Business District Lighting Upgrades n/a 20-CIP-S002 575,000200,000 90,000 225,000 60,000City Street Lighting Upgrades n/a 20-CIP-S005 590,000590,000Minnetonka Mills/5th St N Signal Replacement 5 23-CIP-S007 250,000130,000 120,000Mainstreet Banner Pole Installation n/a 23-CIP-S008 200,00050,000 50,000 50,000 50,000Excelsrior Blvd. Fencing n/a 22,908,0004,105,000 4,057,000 3,851,500 5,871,000 5,023,500PI - PIR/General Obligation Bonds Total RF - Refuse Fund 08-CIP-B022 50,00050,000Public Works - Replace Roofing n/a 08-CIP-B023 18,00018,000Public Works - Replace Overhead Doors n/a 68,00018,000 50,000RF - Refuse Fund Total SA - Special Assessment 01-CIP-S101 3,510,000810,000 600,000 600,000 850,000 650,000Residential Street Improvements and Utilities n/a 3,510,000810,000 600,000 600,000 850,000 650,000SA - Special Assessment Total SF - Sanitary Sewer Fund 01-CIP-S101 6,770,0001,230,000 1,090,000 1,090,000 1,710,000 1,650,000Residential Street Improvements and Utilities n/a 08-CIP-B022 250,000250,000Public Works - Replace Roofing n/a 08-CIP-B023 18,00018,000Public Works - Replace Overhead Doors n/a 18-CIP-U016 275,00060,000 65,000 75,000 75,000Sewer Lining 2 23-CIP-U020 1,100,0001,100,000Citywide Meter Replacement n/a 23-CIP-U022 375,000175,000 200,000SCADA Fiber Project n/a 8,788,0002,565,000 1,355,000 1,183,000 2,035,000 1,650,000SF - Sanitary Sewer Fund Total Wednesday, November 15, 2023 41 TotalSourceProject #Priority 2024 2025 2026 2027 2028 SU - Storm Sewer Fund 01-CIP-S101 2,090,000420,000 245,000 245,000 640,000 540,000Residential Street Improvements and Utilities n/a 01-CIP-U002 146,50027,000 28,000 29,000 30,000 32,500Storm Drainage System Maintenance - Alley Repairs n/a 08-CIP-B022 250,000250,000Public Works - Replace Roofing n/a 08-CIP-B023 18,00018,000Public Works - Replace Overhead Doors n/a 20-CIP-S005 10,00010,000Minnetonka Mills/5th St N Signal Replacement 5 2,514,500447,000 273,000 292,000 930,000 572,500SU - Storm Sewer Fund Total WF - Water Fund 01-CIP-S101 5,798,0001,350,000 1,190,000 1,190,000 1,890,000 178,000Residential Street Improvements and Utilities n/a 08-CIP-B022 250,000250,000Public Works - Replace Roofing n/a 08-CIP-B023 18,00018,000Public Works - Replace Overhead Doors n/a 19-CIP-U017 5,000,0005,000,000Trunk Water Main Rehabilitation 2 23-CIP-U018 290,000270,000 20,000Water Treatment Plant - Roof Replacement n/a 23-CIP-U019 25,00025,000Well #5 Roof Replacement 1 23-CIP-U020 1,100,0001,100,000Citywide Meter Replacement n/a 23-CIP-U021 250,000250,000Lift Station No. 2 n/a 23-CIP-U022 375,000175,000 200,000SCADA Fiber Project n/a 13,106,0002,900,000 1,390,000 1,478,000 7,140,000 198,000WF - Water Fund Total 58,676,00011,842,000 8,782,500 8,948,500 17,849,000 11,254,000GRAND TOTAL Wednesday, November 15, 2023 42 Project Descriptions And Narratives 43 44 General Public Buildings 45 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact Facilities Director 2024 2028thru Department City Hall Administration Description 10 Ton Heating and Air Conditioning Unit for City Hall Council Chambers Project #09-CIP-CH032 Priority n/a Justification Unit was replaced in 2004, needs to be put on schedule. Budget Impact/Other Useful Life 20 yearsProject Name Council Chambers HVAC Unit Category Bldg: City Hall Type Improvement Future Total Project Cost:$18,000 Total20242025202620272028Expenditures 18,00018,000Construction/Maintenance 18,000 18,000Total Total20242025202620272028Funding Sources 18,00018,000CI - Capital Improvement Fund 18,000 18,000Total Wednesday, November 15, 2023 46 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact Facilities Director 2024 2028thru Department City Hall Administration Description Rooftop units for City Hall upper and lower level. One 10 ton and one 17 ton. Project #09-CIP-CH035 Priority n/a Justification Existing Units were installed in 2007. Budget Impact/Other Useful Life 20 yearsProject Name City Hall AC Rooftop Units Category Bldg: City Hall Type Improvement Future Total Project Cost:$60,000 Total20242025202620272028Expenditures 60,00060,000Construction/Maintenance 60,000 60,000Total Total20242025202620272028Funding Sources 60,00060,000CI - Capital Improvement Fund 60,000 60,000Total Wednesday, November 15, 2023 47 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact Bldg/Equip Supt 2024 2028thru Department City Hall Administration Description Project #23-CIP-CH038 Priority n/a Justification Budget Impact/Other Useful LifeProject Name City Hall/Police Station - Roof Replacement Category Bldg: City Hall Type Improvement Future Total Project Cost:$990,000 Total20242025202620272028Expenditures 990,000140,000 850,000Construction/Maintenance 140,000 850,000 990,000Total Total20242025202620272028Funding Sources 990,000140,000 850,000CI - Capital Improvement Fund 140,000 850,000 990,000Total Wednesday, November 15, 2023 48 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact Facilities Director 2024 2028thru Department Comm Svcs - Activity Center Description Replace and repair mortar joints, replace damaged bricks and repair sagging window lintels. Project #22-CIP-AC052 Priority 2 Very Important Justification Brick exterior has major and minor cracking and loose mortar joints. Thre are damaged or cracked bricks that need to be removed and replaced. Two window lintels are bowing and need replacement. Budget Impact/Other Useful Life 20 yearsProject Name Activity Center - Tuckpointing & Repair of Brick Category Buildings: Activity Center Type Improvement Future Total Project Cost:$120,000 Total20242025202620272028Expenditures 120,000120,000Construction/Maintenance 120,000 120,000Total Total20242025202620272028Funding Sources 120,000120,000CI - Capital Improvement Fund 120,000 120,000Total Wednesday, November 15, 2023 49 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact 2024 2028thru Department Comm Svcs - Activity Center Description Project #23-CIP-AC053 Priority n/a Justification Budget Impact/Other Useful LifeProject Name Activity Center - Roof Replacement & Flashing Category Buildings: Activity Center Type Improvement Future Total Project Cost:$250,000 Total20242025202620272028Expenditures 250,000250,000Construction/Maintenance 250,000 250,000Total Total20242025202620272028Funding Sources 250,000250,000CI - Capital Improvement Fund 250,000 250,000Total Wednesday, November 15, 2023 50 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact 2024 2028thru Department Comm Svcs - Activity Center Description Remove existing flooring and prep area Install new flooring Project #23-CIP-AC054 Priority n/a Justification The entry area flooring is worn. The tile is difficult to keep clean and the transition between tile and vinyl can cause a tripping hazard. Budget Impact/Other Useful LifeProject Name Floor Covering - Entry, Commons and Dining Area Category Buildings: Activity Center Type Improvement Future Total Project Cost:$39,500 Total20242025202620272028Expenditures 39,50039,500Construction/Maintenance 39,500 39,500Total Total20242025202620272028Funding Sources 39,50039,500CI - Capital Improvement Fund 39,500 39,500Total Wednesday, November 15, 2023 51 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact 2024 2028thru Department Comm Svcs - Activity Center Description Project #23-CIP-AC055 Priority n/a Justification Budget Impact/Other Useful Life 15 yearsProject Name Activity Center - Countertops Category Buildings: Activity Center Type Improvement Future Total Project Cost:$10,000 Total20242025202620272028Expenditures 10,00010,000Construction/Maintenance 10,000 10,000Total Total20242025202620272028Funding Sources 10,00010,000CI - Capital Improvement Fund 10,000 10,000Total Wednesday, November 15, 2023 52 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact 2024 2028thru Department Comm Svcs - Activity Center Description Remove and replace existing worn aluminum doors, card reader, aluminium transom frame, handicap operator and all existing door hardware. Install new frame, and furnish and install two new doors. Reinstall existing handicap operator. Project #23-CIP-AC056 Priority n/a Justification The doors are part their life span and don't open and close properly. Budget Impact/Other Useful LifeProject Name Activity Center - Main Interior Door Replacement Category Buildings: Activity Center Type Improvement Future Total Project Cost:$18,500 Total20242025202620272028Expenditures 18,50018,500Construction/Maintenance 18,500 18,500Total Total20242025202620272028Funding Sources 18,50018,500CI - Capital Improvement Fund 18,500 18,500Total Wednesday, November 15, 2023 53 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact Arts Center Director 2024 2028thru Department Comm Svcs - Arts Center Description Prep work area Paint walls and soffit in theater and side vestibules of Main Theater Paint metal handrails Paint metal door frames and metal doors Apply 2 coats of paint to all surfaces Price includes paint, supplies, materials and labor If brushing and rolling does not apply over rough block, then spraying will need to take place. If spraying is needed additional charges will apply covering and prep Reupholster Fabric Sound walls in back of theater to match paint color Project #14-CIP-AR003 Priority 2 Very Important Justification The Theater has not been painted since 1997 when built. The theater seats have been recovered, the carpet has been replaced and the wall color is dated and needs a freshening up. As the highlight of the building, the theater's appearance is of utmost importance. Budget Impact/Other Did not complete in 2015, moving project forward Useful Life 15 yearsProject Name Arts Center - Paint Theatre Category Buildings: Arts Center Type Improvement Future Total Project Cost:$52,086 Total20242025202620272028Expenditures 28,00028,000Construction/Maintenance 28,000 28,000Total Total20242025202620272028Funding Sources 28,00028,000AC - Arts Center Fund 28,000 28,000Total Wednesday, November 15, 2023 54 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact Arts Center Director 2024 2028thru Department Comm Svcs - Arts Center Description This project was originally slated for 2019, but tabled for further planning and city guideline revisions This is a multi-phase project: Phase 1: Replace existing name signage with imporved and refreshed outdoor signage on front of building Phase 2: Create signage/marquee/sculptural piece in front of Center that clearly identifies the building as Hopkins Center for the Arts Phase 3: Continue impage improvements Project #19-CIP-AR002 Priority 2 Very Important Justification Currently the signage for Hopkins Center for the Arts is obstructed by trees and in need of updates. Stages Theatre signage is more visible causing confusion regarding the building. This project is estimated to exceed $100,000. Part of the funding for this project will be raised through donations with assistance from the Friends and City leadership. Budget Impact/Other Useful Life 20 yearsProject Name Arts Center - Outdoor Signage/lighting Category Buildings: Arts Center Type Improvement Future Total Project Cost:$75,000 Total20242025202620272028Expenditures 50,00025,000 25,000Construction 25,000 25,000 50,000Total Total20242025202620272028Funding Sources 50,00025,000 25,000AC - Arts Center Fund 25,000 25,000 50,000Total Wednesday, November 15, 2023 55 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact Arts Center Director 2024 2028thru Department Comm Svcs - Arts Center Description Access Control System with Lockdown Capacity including equipment and installation. Phase 1: $43,500 Phase 2: $32,000 Phase 3: $27,000 Phase 1 & 2 completed in 2024/2025. Install locking and security mechanisms that will allow for panic button locking system in an emergency lockdown situation throughout the building. System will be integrated with security camera system. Project #19-CIP-AR005 Priority 2 Very Important Justification Installing keycard access would allow better control of who is allowed to enter the building as well as the ability to track who is in the building. Stages Theatre Company has many staff members, and many who are contracted, working as needed on a project. The contracted employees are given keys when needed, however, from a building management standpoint, it is difficult to track and make sure that people don't have access to the building that shouldn't. Long-term the goal is to key all interior office and room doors with the same system, primarily to be able to keep key situation under better control and to allow for a safe lock-down procedure if ever needed. Budget Impact/Other Useful LifeProject Name Arts Center - Access/Lockdown System Category Buildings: Arts Center Type Improvement Future Total Project Cost:$190,500 Total20242025202620272028Expenditures 102,50012,500 60,000 30,000 0Construction/Maintenance 12,500 60,000 30,000 0 102,500Total Total20242025202620272028Funding Sources 102,50012,500 60,000 30,000 0AC - Arts Center Fund 12,500 60,000 30,000 0 102,500Total Wednesday, November 15, 2023 56 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact Arts Center Director 2024 2028thru Department Comm Svcs - Arts Center Description Replacement of Roof Project #19-CIP-AR007 Priority 2 Very Important Justification Facility originally built in 1997. Budget Impact/Other Useful LifeProject Name Arts Center - Roof Replacement Category Buildings: Arts Center Type Improvement Future Total Project Cost:$750,000 Total20242025202620272028Expenditures 750,000750,000Construction 750,000 750,000Total Total20242025202620272028Funding Sources 375,000375,000AC - Arts Center Fund 375,000375,000CI - Capital Improvement Fund 750,000 750,000Total Wednesday, November 15, 2023 57 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact Arts Center Director 2024 2028thru Department Comm Svcs - Arts Center Description Replace non-functional hardware on front exterior and interior doors so they properly lock and function Replace SW and NW exterior doors Project #23-CIP-AR004 Priority n/a Justification Due to age, the front exterior and interior doors and hardware are failing and causing safety concerns The SW and NW doors are rusted and the mechanism used for large deliveries into the building no long work properly Budget Impact/Other Useful LifeProject Name Arts Center - Exterior Door Repairs Category Buildings: Arts Center Type Unassigned Future Total Project Cost:$50,500 Total20242025202620272028Expenditures 50,50050,500Construction/Maintenance 50,500 50,500Total Total20242025202620272028Funding Sources 50,50050,500AC - Arts Center Fund 50,500 50,500Total Wednesday, November 15, 2023 58 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact Arts Center Director 2024 2028thru Department Comm Svcs - Arts Center Description Additional and upgraded security cameras to be installed at the Arts Center. Project #23-CIP-AR005 Priority 1 Urgent Justification Requested cameras would be used for the security of the Arts Center Building and also be able to assist in providing the Police Department camera footage for events that occur along mainstreet. Budget Impact/Other Useful LifeProject Name Arts Center - Security Cameras Category Buildings: Arts Center Type Improvement Future Total Project Cost:$22,500 Total20242025202620272028Expenditures 22,50022,500Construction 22,500 22,500Total Total20242025202620272028Funding Sources 22,50022,500AC - Arts Center Fund 22,500 22,500Total Wednesday, November 15, 2023 59 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact Facilities Director 2024 2028thru Department Fire Description Replace 35 ton Air Handling Unit Project #08-CIP-B121 Priority n/a Justification Budget Impact/Other Useful LifeProject Name Fire Station: Replace 25 Ton AHU Category Buildings: Fire Facilities Type Improvement Future Total Project Cost:$92,000 Total20242025202620272028Expenditures 92,00092,000Construction/Maintenance 92,000 92,000Total Total20242025202620272028Funding Sources 92,00092,000CI - Capital Improvement Fund 92,000 92,000Total Wednesday, November 15, 2023 60 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact Facilities Director 2024 2028thru Department Fire Description Replace roof Project #08-CIP-B125 Priority n/a Justification Budget Impact/Other Useful LifeProject Name Fire - Replace Roof Category Buildings: Fire Facilities Type Improvement Future Total Project Cost:$550,000 Total20242025202620272028Expenditures 550,000550,000Construction/Maintenance 550,000 550,000Total Total20242025202620272028Funding Sources 550,000550,000CI - Capital Improvement Fund 550,000 550,000Total Wednesday, November 15, 2023 61 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact Pavilion Manager 2024 2028thru Department Pavilion Description Replace the mezzanine vinyl tile with rubber flooring. Project #20-CIP-PV333 Priority 3 Important Justification Current flooring has cracks, gouges, and severe wear areas. Rubber floor is easier maintain and is more durable and versitle than vinyl tile. Budget Impact/Other Useful Life 20 yearsProject Name Pavilion - Mezzanine Flooring Replacement Category Bldgs: Pavillion Type Improvement Future Total Project Cost:$25,000 Total20242025202620272028Expenditures 25,00025,000Construction/Maintenance 25,000 25,000Total Total20242025202620272028Funding Sources 25,00025,000PA - Pavilion Fund 25,000 25,000Total Wednesday, November 15, 2023 62 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact Pavilion Manager 2024 2028thru Department Pavilion Description Replace the arena exit doors, frames, hinges, and closers. Project #20-CIP-PV334 Priority 3 Important Justification The frames and hardware are original, installed during the construction of the facility. Frames are rusting and hardware is failing. Budget Impact/Other Useful Life 15-20 yearsProject Name Pavilion - Arena Exit Door Replacement Category Bldgs: Pavillion Type Improvement Future Total Project Cost:$115,000 Total20242025202620272028Expenditures 115,000115,000Construction/Maintenance 115,000 115,000Total Total20242025202620272028Funding Sources 115,000115,000PA - Pavilion Fund 115,000 115,000Total Wednesday, November 15, 2023 63 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact Facilities Director 2024 2028thru Department Pavilion Description Replace the three 100 gallon water heaters that are used to supply hot water to the bathrooms and hot water used for ice resurfacing. Project #22-CIP-PV335 Priority n/a Justification The water heaters are at the end of useful life and in need of replacing. Budget Impact/Other Useful LifeProject Name Pavilion - Water Heater Replacement Category Bldgs: Pavillion Type Unassigned Future Total Project Cost:$50,000 Total20242025202620272028Expenditures 50,00050,000Construction/Maintenance 50,000 50,000Total Total20242025202620272028Funding Sources 50,00050,000PA - Pavilion Fund 50,000 50,000Total Wednesday, November 15, 2023 64 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact Facilities Director 2024 2028thru Department Pavilion Description Replace South Team Room Addition Roof Project #23-CIP-PV336 Priority n/a Justification Budget Impact/Other Useful LifeProject Name Pavilion - Roof Replacement Category Bldgs: Pavillion Type Unassigned Future Total Project Cost:$100,000 Total20242025202620272028Expenditures 100,000100,000Construction/Maintenance 100,000 100,000Total Total20242025202620272028Funding Sources 100,000100,000PA - Pavilion Fund 100,000 100,000Total Wednesday, November 15, 2023 65 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact Facilities Director 2024 2028thru Department Pavilion Description Replace existing radiant heating system above the bleachers in the arena. Project #23-CIP-PV337 Priority 3 Important Justification Current system is at the end of useful life and major components will need replacing. Budget Impact/Other Useful Life 10-20 yearsProject Name Pavilion - Bleacher Heating Replacement Category Bldgs: Pavillion Type Improvement Future Total Project Cost:$75,000 Total20242025202620272028Expenditures 75,00075,000Construction/Maintenance 75,000 75,000Total Total20242025202620272028Funding Sources 75,00075,000PA - Pavilion Fund 75,000 75,000Total Wednesday, November 15, 2023 66 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact Facilities Director 2024 2028thru Department Pavilion Description Replace four doors in the arena that were not included in the 2018 improvement. Project #23-CIP-PV338 Priority 3 Important Justification Two of the doors are original to the 1990 construction of the Pavilion and the other two were installed as part of the 2004 team room addition. All four doors are damaged and need replacing to a more vandal proof model. Budget Impact/Other Useful Life 10-20 yearsProject Name Pavilion - Door Replacement Category Bldgs: Pavillion Type Improvement Future Total Project Cost:$23,000 Total20242025202620272028Expenditures 23,00023,000Construction/Maintenance 23,000 23,000Total Total20242025202620272028Funding Sources 23,00023,000PA - Pavilion Fund 23,000 23,000Total Wednesday, November 15, 2023 67 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact Facilities Director 2024 2028thru Department Pavilion Description Add window blinds to windows in the warming house Project #23-CIP-PV339 Priority 3 Important Justification Budget Impact/Other Useful LifeProject Name Pavilion - Warming House Window Blinds Category Bldgs: Pavillion Type Improvement Future Total Project Cost:$14,000 Total20242025202620272028Expenditures 14,00014,000Construction 14,000 14,000Total Total20242025202620272028Funding Sources 14,00014,000PA - Pavilion Fund 14,000 14,000Total Wednesday, November 15, 2023 68 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact Facilities Director 2024 2028thru Department Public Works: Bldg/Equip Ser Description Replace Roofing, Vehicle Storage and Office area Project #08-CIP-B022 Priority n/a Justification Budget Impact/Other Useful LifeProject Name Public Works - Replace Roofing Category Buildings: Public Works Type Improvement Future Total Project Cost:$1,600,000 Total20242025202620272028Expenditures 1,600,0001,600,000Construction/Maintenance 1,600,000 1,600,000Total Total20242025202620272028Funding Sources 800,000800,000CI - Capital Improvement Fund 50,00050,000RF - Refuse Fund 250,000250,000SF - Sanitary Sewer Fund 250,000250,000SU - Storm Sewer Fund 250,000250,000WF - Water Fund 1,600,000 1,600,000Total Wednesday, November 15, 2023 69 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact Facilities Director 2024 2028thru Department Public Works: Bldg/Equip Ser Description Replace overhead doors Project #08-CIP-B023 Priority n/a Justification Budget Impact/Other Inspected in 2019, will move from 2020 to 2022. Useful LifeProject Name Public Works - Replace Overhead Doors Category Buildings: Public Works Type Improvement Future Total Project Cost:$90,000 Total20242025202620272028Expenditures 90,00090,000Construction/Maintenance 90,000 90,000Total Total20242025202620272028Funding Sources 18,00018,000CI - Capital Improvement Fund 18,00018,000RF - Refuse Fund 18,00018,000SF - Sanitary Sewer Fund 18,00018,000SU - Storm Sewer Fund 18,00018,000WF - Water Fund 90,000 90,000Total Wednesday, November 15, 2023 70 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact Facilities Director 2024 2028thru Department Public Works: Bldg/Equip Ser Description The current windows are well past their useful life. 8 Windows and two doors are due for replacement. Project #21-CIP-B101 Priority 5 Future Consideration Justification The need to get this facility into the CIP for future planning. Installing new windows and doors will be more energy efficent for the building. Today's estimated cost is $55,000. Budget Impact/Other Useful Life 20 yearsProject Name 907 Mainstreet (HHS) Windows & Front/Back Door Category Economic Development Type Improvement Future Total Project Cost:$105,000 Total20242025202620272028Expenditures 105,000105,000Construction/Maintenance 105,000 105,000Total Total20242025202620272028Funding Sources 105,000105,000CI - Capital Improvement Fund 105,000 105,000Total Wednesday, November 15, 2023 71 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact Facilities Director 2024 2028thru Department Public Works: Bldg/Equip Ser Description Purchase and install a drive over undercarriage wash system for the equipment wash bay. Project #22-CIP-B102 Priority 3 Important Justification Currently the was bay does not have an efficient process to rinse sale and direct from underneath vehicles and equipment. An undercarriage pressure washing system is a fast and effective way to rinse the salt, snow and ice that collects when plowing and will aide in the prevention of rust and prolong the useful life of equipment and lower maintenance costs. Budget Impact/Other Useful Life 20 yearsProject Name Undercarriage Wash System Category Buildings: Public Works Type Improvement Future Total Project Cost:$70,000 Total20242025202620272028Expenditures 70,00070,000Construction/Maintenance 70,000 70,000Total Total20242025202620272028Funding Sources 70,00070,000CI - Capital Improvement Fund 70,000 70,000Total Wednesday, November 15, 2023 72 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact 2024 2028thru Department Public Works: Bldg/Equip Ser Description Replace and add more sensors to boilers, RTUs, VAVs, and CUHs at City Hall, Police Department and Fire Department. Perform BAS software upgrade. Project #23-CIP-B103 Priority 2 Very Important Justification Current sensors are outdated and replacement sensors are difficult to find. Adding sensors to systems will increase efficiency and save energy. Budget Impact/Other Useful Life 10 yearsProject Name Building Automation System-Replacements & Upgrades Category Buildings - Multiple Type Improvement Future Total Project Cost:$60,000 Total20242025202620272028Expenditures 60,00060,000Equipment 60,000 60,000Total Total20242025202620272028Funding Sources 60,00060,000CI - Capital Improvement Fund 60,000 60,000Total Wednesday, November 15, 2023 73 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact Facilities Director 2024 2028thru Department Public Works: Bldg/Equip Ser Description Replace all four roofs at the parking ramp. Project #23-CIP-B104 Priority n/a Justification Roofs were identified in the roof study as in need of replacement. Budget Impact/Other Useful LifeProject Name Parking Ramp Roof Replacement Category Trans: Parking Facilities Type Unassigned Future Total Project Cost:$75,000 Total20242025202620272028Expenditures 75,00075,000Construction/Maintenance 75,000 75,000Total Total20242025202620272028Funding Sources 75,00075,000CI - Capital Improvement Fund 75,000 75,000Total Wednesday, November 15, 2023 74 Parks and Recreation 75 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact Public Works Director 2024 2028thru Department Public Works: Parks Description Oakes Park - Reconstruct tennis courts pavement - $130,000 Cottageville Park - Rehab basketball court $60,000 Interlachen Basketball court - $40,000 Project #13-CIP-P044 Priority 2 Very Important Justification Tennis courts are badly cracked, no longer repairable. Basketball court pavement deteriorated, needs upgraded hoops and goal standards. Budget Impact/Other Useful LifeProject Name Improve Courts: Oakes, Cottageville & Interlachen Category Parks/Fores/Pav.: Comm. Facil. Type Improvement Future Total Project Cost:$250,000 Total20242025202620272028Expenditures 230,000230,000Construction/Maintenance 230,000 230,000Total Total20242025202620272028Funding Sources 230,000230,000PDF- Park Dedication Fund 230,000 230,000Total Wednesday, November 15, 2023 76 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact Public Works Director 2024 2028thru Department Public Works: Parks Description Remove and replace existing asphalt pavement and apply new color coatings system. Project #21-CIP-P073 Priority 1 Urgent Justification The court is deteriorated beyond crack sealing or top coat repairs. Needs new asphalt pavement and color coatings. Budget Impact/Other Useful LifeProject Name Repair Valley ParkVolleytball Court Category PW - Parks Type Improvement Future Total Project Cost:$70,000 Total20242025202620272028Expenditures 70,00070,000Construction/Maintenance 70,000 70,000Total Total20242025202620272028Funding Sources 70,00070,000PDF- Park Dedication Fund 70,000 70,000Total Wednesday, November 15, 2023 77 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact Public Works Director 2024 2028thru Department Public Works: Parks Description Remove and replace existing asphalt pavement and apply new color coatings system. Project #21-CIP-P074 Priority n/a Justification The court is deteriorated beyond crack sealing or top coat repairs. Needs new asphalt pavement and color coatings. Budget Impact/Other Useful LifeProject Name Repair Burnes Park Tennis Courts Category PW - Parks Type Improvement Future Total Project Cost:$130,000 Total20242025202620272028Expenditures 130,000130,000Construction/Maintenance 130,000 130,000Total Total20242025202620272028Funding Sources 130,000130,000PDF- Park Dedication Fund 130,000 130,000Total Wednesday, November 15, 2023 78 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact Public Works Director 2024 2028thru Department Public Works: Parks Description Remove and replace existing asphalt pavement. Project #21-CIP-P075 Priority n/a Justification The court is deteriorated beyond crack sealing or top coat repairs. Needs new asphalt pavement. Budget Impact/Other Useful LifeProject Name Repair Play Courts- Elmo & Park Valley Category PW - Parks Type Unassigned Future Total Project Cost:$80,000 Total20242025202620272028Expenditures 80,00080,000Construction/Maintenance 80,000 80,000Total Total20242025202620272028Funding Sources 80,00080,000PDF- Park Dedication Fund 80,000 80,000Total Wednesday, November 15, 2023 79 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact Public Works Director 2024 2028thru Department Public Works: Parks Description Next step in Master Park Plan. Moving forward on planning and phase options. Project #23-CIP-P076 Priority n/a Justification Central is the Park in most need of improvements Budget Impact/Other Useful LifeProject Name Central Park Master Plan Category PW - Parks Type Improvement Future Total Project Cost:$150,000 Total20242025202620272028Expenditures 150,000150,000Planning/Design 150,000 150,000Total Total20242025202620272028Funding Sources 150,000150,000PDF- Park Dedication Fund 150,000 150,000Total Wednesday, November 15, 2023 80 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact Management Analyst 2024 2028thru Department Recreation Description The joint recreation agreement in place between the cities of Hopkins and Minnetonka provides for the sharing of operational and maintenance expenses for Shady Oak Beach. These expenses are split 33% city of Hopkins and 67% city of Minnetonka. Shady Oak Beach is operated from June - August annually; however the park is available for use year round. 2021: Dock maintenance ($10,000) 2022: Miscellaneous building components, i.e. installation of energy efficient lighting in restrooms/gate area, patio tables and chairs ($15,000); inflatables replacement ($10,000) 2023: Miscellaneous building maintenance ($10,000) 2024: Inflatable replacement ($10,000) 2025: Miscellaneous building maintenance ($10,000) Project #16-CIP-R003 Priority 3 Important Justification Shady Oak Beach is jointly operated by the cities of Hopkins and Minnetonka. The facility is open from June - August each summer with the revenues generated from season pass sales and daily admissions. The facility was most recently renovated in 1998. An addiitional renovation on the lifeguard shack was completed in 2021. 2023: Miscellaneous building/grounds maintenance; miscellaneous building equipment/components, i.e. concession equipment, patio tables and chairs 2024: Inflatable replacement ($10,000); parking lot mill and overlay ($80,000) 2025: Miscellaneous building maintenance 2026: Miscellaneous building maintenance 2027: Miscellaneous building maintenance Budget Impact/Other Useful Life 10-20 yearsProject Name Shady Oak Beach Improvements Category PW - Parks Type Improvement Future Total Project Cost:$475,000 Total20242025202620272028Expenditures 140,00090,000 20,000 10,000 10,000 10,000Construction/Maintenance 90,000 20,000 10,000 10,000 10,000 140,000Total Total20242025202620272028Funding Sources 93,80060,300 13,400 6,700 6,700 6,700GU - Other Governmental Units 46,20029,700 6,600 3,300 3,300 3,300PDF- Park Dedication Fund 90,000 20,000 10,000 10,000 10,000 140,000Total Wednesday, November 15, 2023 81 82 Streets, Traffic & Transportation 83 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact Public Works Director 2024 2028thru Department Public Works: Streets/Traffic Description Locations to be determined consistent with the street reconstruction program. Program includes reconstruction of deteriorated water main, sanitary sewer and storm sewer in conjunction with street improvement projects. Utility improvements are consistent with the Storm Water Management Plan, Water and Sewer Utility Master Plan, and televised inspections. 2024-2027: Central Avenues Reconstruction 2028: South Avenues (14th, 15th, 16th and 17th) Project #01-CIP-S101 Priority n/a Justification In most cases where street reconstruction takes place, storm sewer facilities either need upgrading or need to be installed new. In most cases, water main and sanitary sewer need to be rehabilitated in conjunction with street reconstruction. The costs assume the city funding 100% of major storm sewer, water main, and sanitary sewer improvements. Budget Impact/Other Public Hearing - year prior to planned construction Plans and specifications - year prior to planned construction Bid - year of planned construction Consistent with the Storm Water Management Plan, Water and Sewer Utility Master Plan, and television inspections. Consistent with the City Council adopted Roadway Improvement Policy, Street Ratings, Pavement Management Program, Storm Water Management Plan, Water and Sewer Utility Master Plan, and televised inspections. Useful Life UnassignedProject Name Residential Street Improvements and Utilities Category Trans: Streets Type Improvement Future Total Project Cost:$87,780,000 Total20242025202620272028Expenditures 36,538,0007,420,000 6,165,000 6,165,000 9,490,000 7,298,000Construction/Maintenance 7,420,000 6,165,000 6,165,000 9,490,000 7,298,000 36,538,000Total Total20242025202620272028Funding Sources 18,370,0003,610,000 3,040,000 3,040,000 4,400,000 4,280,000PI - PIR/General Obligation Bonds 3,510,000810,000 600,000 600,000 850,000 650,000SA - Special Assessment 6,770,0001,230,000 1,090,000 1,090,000 1,710,000 1,650,000SF - Sanitary Sewer Fund 2,090,000420,000 245,000 245,000 640,000 540,000SU - Storm Sewer Fund 5,798,0001,350,000 1,190,000 1,190,000 1,890,000 178,000WF - Water Fund 7,420,000 6,165,000 6,165,000 9,490,000 7,298,000 36,538,000Total Wednesday, November 15, 2023 84 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact Public Works Director 2024 2028thru Department Public Works: Streets/Traffic Description County Road 3 from Shady Oak Road to Meadowbrook Road. Lighting, landscaping, street, etc. improvements along Excelsior Boulevard from the east to west city limits. GO Bond payments to be financed by a combination of existing TIF revenue, Municipal State Aid road funds, additional TIF revenue created by economic development, grant funds, and, as a last resort, general city revenue Project has been delayed pending county funding for remaining 4th segement. Project #01-CIP-S104 Priority n/a Justification Deficiencies in terms of roadway condition, traffic/pedestrian movement, safety and aesthetics appear in remaining segment of County Road 3. Segment 4 from Blake Road to Meadowbrook Road; upgrade roadway, implement beautification program. Budget Impact/Other GO bond payments to be financed by a combination of existing TIF revenue, Municipal State Aid road funds, additional TIF revenue created by economic development, grant funds, and, as a last resort, general city revenue. Segment 4: Planning and acquisition - Not in County Funding Plan, when funded city will complete our portion. Consistent with Hennepin County CIP and City Council action. Useful Life UnassignedProject Name County Road 3 Category Trans: Streets Type Improvement Future Total Project Cost:$2,300,000 Total20242025202620272028Expenditures 2,300,0002,300,000Construction/Maintenance 2,300,000 2,300,000Total Total20242025202620272028Funding Sources 1,600,0001,600,000GU - Other Governmental Units 700,000700,000MS - Municipal State Aid Streets 2,300,000 2,300,000Total Wednesday, November 15, 2023 85 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact Public Works Director 2024 2028thru Department Public Works: Streets/Traffic Description Painting bike lanes, constructing trails and sidewalks, safety improvements and other general pedestrian and bicycle improvements to the system. 2025: Upgrade of the 11th Ave South pedestrian crossings in the Wesbrooke Area to pedestrian activated RRFB. Project #13-CIP-S040 Priority n/a Justification Council adopted plan to increase pedestrian and bicycle access and safety, these improvements begin to implement that plan. The existing overhead flushers provide very little benefit. Pedestrian activated rectangular rapid flushing beacons (RRFB) have shown to provide very high compliance for motorists and increases pedestrian safety and comfort. Budget Impact/Other Useful Life 20 yearsProject Name Pedestrian & Bicycle Access Improvements Category Trans: Streets Type Improvement Future Total Project Cost:$465,000 Total20242025202620272028Expenditures 215,00025,000 100,000 27,500 30,000 32,500Construction/Maintenance 25,000 100,000 27,500 30,000 32,500 215,000Total Total20242025202620272028Funding Sources 215,00025,000 100,000 27,500 30,000 32,500PI - PIR/General Obligation Bonds 25,000 100,000 27,500 30,000 32,500 215,000Total Wednesday, November 15, 2023 86 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact Public Works Director 2024 2028thru Department Public Works: Streets/Traffic Description Location to be determined based on Pavement Management Program. Program includes mill and overlay of deteriorated pavements to extend the useful life of the street. Streets for this method of rehabilitation have usually been rehabilitated or reconstructed within the last 20 years. 2024; Central Avenues 2025: Central Avenues 2026 Central Avenues 2027: Central Avenues 2028: 12th, 13th, 15th and 16th Ave South Project #16-CIP-S041 Priority n/a Justification Properly timed mill and overlay projects can significantly extend the life of a street and delay the need for reconstruction. Mill and overlay projects also require less disturbance and are shorter in duration than reconstruction, which results in less impact of the traveling public. Budget Impact/Other Increased 2023 amount by $70,000 from original 2023-2027 CIP. Amendment considered by City Council on May 16, 2023. Useful LifeProject Name Street Rehabilitation Improvements Category Trans: Streets Type Improvement Future Total Project Cost:$5,670,000 Total20242025202620272028Expenditures 2,550,000450,000 475,000 500,000 550,000 575,000Construction/Maintenance 450,000 475,000 500,000 550,000 575,000 2,550,000Total Total20242025202620272028Funding Sources 2,550,000450,000 475,000 500,000 550,000 575,000PI - PIR/General Obligation Bonds 450,000 475,000 500,000 550,000 575,000 2,550,000Total Wednesday, November 15, 2023 87 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact Public Works Director 2024 2028thru Department Public Works: Streets/Traffic Description Replacement of aged regulatory and warning signs that have lost minimum retroreflectivity and replacement of posts, when needed. Project #16-CIP-S042 Priority n/a Justification The city is required to have a sign management program which includes a sign replacement strategy to ensure regulatory and warning signs provide adequate retroreflectivity. Sign replacement cycle is 8 years. Estimated costs assume sign replacements by contract. Parking signs will be replaced as needed due to age, fading, etc. Sign inventory data base will be updated to reflect install date/sign age. Budget Impact/Other Useful LifeProject Name Street Sign Management Category Trans: Streets Type Improvement Future Total Project Cost:$278,000 Total20242025202620272028Expenditures 118,00020,000 22,000 24,000 26,000 26,000Construction/Maintenance 20,000 22,000 24,000 26,000 26,000 118,000Total Total20242025202620272028Funding Sources 118,00020,000 22,000 24,000 26,000 26,000PI - PIR/General Obligation Bonds 20,000 22,000 24,000 26,000 26,000 118,000Total Wednesday, November 15, 2023 88 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact Public Works Director 2024 2028thru Department Public Works: Streets/Traffic Description Upgrade existing lighting in the Central Business District to newer LED fixtures, replace light poles and electrical service feed cabinets, as needed. 2023: Mainstreet East of 5th Ave - 20 fixtures 10th, 11th and 12th Ave N & S of Mainstreet - 52 fixtures Parking Lots 500 and 600 - 15 fixtures 2024: 7th, 8th and 9th Ave N & S of Mainstreet - 28 fixtures Parking Lots 700 and 750 - 8 fixtures Project #20-CIP-S001 Priority n/a Justification There is a need to continue the upgrade of lighting in the Central Business District. The Mainstreet lights were all upgraded to LED fixtures in 2015. An upgrade to LED fixtures will provide energy savings, maintenance savings and create a more uniform lighting appearance throughout the downtown area. Budget Impact/Other Useful LifeProject Name Central Business District Lighting Upgrades Category Trans: Street Lights Type Improvement Future Total Project Cost:$140,000 Total20242025202620272028Expenditures 40,00040,000Construction 40,000 40,000Total Total20242025202620272028Funding Sources 40,00040,000PI - PIR/General Obligation Bonds 40,000 40,000Total Wednesday, November 15, 2023 89 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact Public Works Director 2024 2028thru Department Public Works: Streets/Traffic Description Street lighting upgrades are needed to replace deteriorated poles, electrical feedpoints and old, energy inefficent fixtures. . 2025: Hobby Acres neighborhood streets, replace 17th poles and fixtures to match Xcel Energy upgraded poles/lights and three electrical feedpoints. 2026: Westbrooke Way street lighting, upgrade 22 lights, poles and wiring via new Xcel Energy agreement to replace expired 30-year agreement 2027: 11th Ave S, south of 7th St S, replace 18 poles and fixtures and one electrical feedpoint. 2028: Upgrade/Replace 8 Power Feed Points Project #20-CIP-S002 Priority n/a Justification A replacement plan is needed as these lighting and electrical feed systems are reaching the end of their useful life, with out-dated electrical cabinets, poles and bases and old, energy inefficent light fixtures. Budget Impact/Other Useful LifeProject Name City Street Lighting Upgrades Category Trans: Street Lights Type Improvement Future Total Project Cost:$875,000 Total20242025202620272028Expenditures 575,000200,000 90,000 225,000 60,000Construction 200,000 90,000 225,000 60,000 575,000Total Total20242025202620272028Funding Sources 575,000200,000 90,000 225,000 60,000PI - PIR/General Obligation Bonds 200,000 90,000 225,000 60,000 575,000Total Wednesday, November 15, 2023 90 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact Public Works Director 2024 2028thru Department Public Works: Streets/Traffic Description Replacement and upgrading of traffic signal infrastructure including poles, mast arms, cabinets and controls, signal heads, pedestrian heads, and pushbuttons.The work will also include upgrading the pedestrian ramps and crossings to meet ADA standards. 2027: Removal and replacement of signal and ADA upgrades Project #20-CIP-S005 Priority 5 Future Consideration Justification The existing signal is old and reaching the end of it's service life. Pedestrian crossing and ADA improvements should be completed as there are increased levels of both pedestrian and vehicular traffic through the intersection since the development of the Excelsior Crossings office park and improvements to Burnes Park. Budget Impact/Other Useful LifeProject Name Minnetonka Mills/5th St N Signal Replacement Category Trans: Sign/Signals Type Improvement Future Total Project Cost:$600,000 Total20242025202620272028Expenditures 600,000600,000Construction/Maintenance 600,000 600,000Total Total20242025202620272028Funding Sources 590,000590,000PI - PIR/General Obligation Bonds 10,00010,000SU - Storm Sewer Fund 600,000 600,000Total Wednesday, November 15, 2023 91 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact 2024 2028thru Department Public Works: Streets/Traffic Description Installation of freestanding banner mount poles for large Mainstreet banners Project #23-CIP-S007 Priority n/a Justification The existing Mainstreet banners are mounted to provate buildings through an agreement between the City and the property owners. The banners have caused significant damage to building brickwork in recent years, requireing extensive and expensive repairs that the City is responsible for. One property owner has expressed that they will not renew the banner attachment agreement when it expires. Freestanding banner mounts would eliminate the need to have the banners mounted to private businesses. Budget Impact/Other Useful LifeProject Name Mainstreet Banner Pole Installation Category Unassigned Type Unassigned Future Total Project Cost:$250,000 Total20242025202620272028Expenditures 250,000130,000 120,000Construction 130,000 120,000 250,000Total Total20242025202620272028Funding Sources 250,000130,000 120,000PI - PIR/General Obligation Bonds 130,000 120,000 250,000Total Wednesday, November 15, 2023 92 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact 2024 2028thru Department Public Works: Streets/Traffic Description Wooden fencing on Excelsior Blvd: South side of South Presidents, South side of 5th St S and 9th Ave S, and North side of Excelsior Blvd. 17th Ave N Project #23-CIP-S008 Priority n/a Justification Posts and panels have been failing for a few years. We need to start replacing so we are not constantly replacing the broken boards Budget Impact/Other Useful LifeProject Name Excelsrior Blvd. Fencing Category Unassigned Type Unassigned Future Total Project Cost:$200,000 Total20242025202620272028Expenditures 200,00050,000 50,000 50,000 50,000Construction/Maintenance 50,000 50,000 50,000 50,000 200,000Total Total20242025202620272028Funding Sources 200,00050,000 50,000 50,000 50,000PI - PIR/General Obligation Bonds 50,000 50,000 50,000 50,000 200,000Total Wednesday, November 15, 2023 93 94 Utilities 95 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact Public Works Director 2024 2028thru Department Public Works: Utilities Description Annual concrete repairs and patching of existing alleys. Project #01-CIP-U002 Priority n/a Justification Annual alley pavement concrete slab repairs are needed. Budget Impact/Other Consistent with the Storm Water Management Plan. Useful Life UnassignedProject Name Storm Drainage System Maintenance - Alley Repairs Category Utilities: Municipal Sanitary Se Type Improvement Future Total Project Cost:$455,500 Total20242025202620272028Expenditures 146,50027,000 28,000 29,000 30,000 32,500Construction/Maintenance 27,000 28,000 29,000 30,000 32,500 146,500Total Total20242025202620272028Funding Sources 146,50027,000 28,000 29,000 30,000 32,500SU - Storm Sewer Fund 27,000 28,000 29,000 30,000 32,500 146,500Total Wednesday, November 15, 2023 96 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact Public Works Director 2024 2028thru Department Public Works: Utilities Description This will help us line our sanitary sewers to eliminate infiltration root intrusion and avoid expensive repairs and sewer backups. Project #18-CIP-U016 Priority 2 Very Important Justification We have an old collection system that needs immediate attention. Continuously cleaning the sewer does not stop roots or infiltration from going into the pipes, we need a more permanent fix. The majority of our sanitary sewer pipe is made out of clay pipe and has reached its life expectancy. Budget Impact/Other Useful LifeProject Name Sewer Lining Category Utilities: Municipal Sanitary Se Type Improvement Future Total Project Cost:$582,500 Total20242025202620272028Expenditures 275,00060,000 65,000 75,000 75,000Construction/Maintenance 60,000 65,000 75,000 75,000 275,000Total Total20242025202620272028Funding Sources 275,00060,000 65,000 75,000 75,000SF - Sanitary Sewer Fund 60,000 65,000 75,000 75,000 275,000Total Wednesday, November 15, 2023 97 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact Public Works Director 2024 2028thru Department Public Works: Utilities Description Program includes rehabilitatation of trunk water mains around the city. Staff has conducted some non-destructive condition assessment testing of various trunk lines around the city. The testing determines a level of deterioration based on a calculated reduction of thickness of the pipe wall. Review of how critical the line is, break records, pipe age, and soil conditions are also considered in determining projects. 2027: Replacement of trunk main as informed by non-destructive testing at various locations. Project #19-CIP-U017 Priority 2 Very Important Justification Trunk water mains are large diameter, high capacity lines that are critical to supply water to and from the water treatment plant, water towers, and d i s t r i b u t i o n l i n e s a r o u n d t h e c i t y a n d c a n n o t e a s i l y b e t a k e n o u t o f s e r v i c e . P u b l i c W o r k s s t a f f h a s b e e n m a n a g i n g t h e t r u n k m a i n s y s t e m a s a standalone asset, as these mains cannot always be included for rehabilitation with street reconstruction projects. Much of the city's trunk system was constructed over 50 years ago and is approaching the end of it's service life. Budget Impact/Other Useful LifeProject Name Trunk Water Main Rehabilitation Category Utilities: Municipal Water Syst Type Improvement Future Total Project Cost:$8,955,000 Total20242025202620272028Expenditures 5,000,0005,000,000Construction/Maintenance 5,000,000 5,000,000Total Total20242025202620272028Funding Sources 5,000,0005,000,000WF - Water Fund 5,000,000 5,000,000Total Wednesday, November 15, 2023 98 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact Public Works Director 2024 2028thru Department Public Works: Utilities Description Project #23-CIP-U018 Priority n/a Justification Budget Impact/Other Useful LifeProject Name Water Treatment Plant - Roof Replacement Category Utilities: Municipal Water Syst Type Improvement Future Total Project Cost:$290,000 Total20242025202620272028Expenditures 290,000270,000 20,000Construction/Maintenance 270,000 20,000 290,000Total Total20242025202620272028Funding Sources 290,000270,000 20,000WF - Water Fund 270,000 20,000 290,000Total Wednesday, November 15, 2023 99 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact Facilities Director 2024 2028thru Department Public Works: Utilities Description Replace the roof at well #5 Project #23-CIP-U019 Priority 1 Urgent Justification Roof is identified in the roof study as in need of replacement Budget Impact/Other Useful Life 25 yearsProject Name Well #5 Roof Replacement Category Utilities: Municipal Water Syst Type Improvement Future Total Project Cost:$25,000 Total20242025202620272028Expenditures 25,00025,000Construction/Maintenance 25,000 25,000Total Total20242025202620272028Funding Sources 25,00025,000WF - Water Fund 25,000 25,000Total Wednesday, November 15, 2023 100 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact 2024 2028thru Department Public Works: Utilities Description Citywide meter replacement. Switch to a fixed network system. Project #23-CIP-U020 Priority n/a Justification Our current system has reached its end of life. The radios for meters are starting to fail at a rapid rate. Radios for current system are no longer available. Switching to a new fixed network will allo the city to have timely data and provide more accurate readings. It will make operations more efficient, reduce costs and be able to promote water conservation and sustainability. Budget Impact/Other Useful LifeProject Name Citywide Meter Replacement Category Unassigned Type Unassigned Future Total Project Cost:$2,200,000 Total20242025202620272028Expenditures 2,200,0002,200,000Construction 2,200,000 2,200,000Total Total20242025202620272028Funding Sources 1,100,0001,100,000SF - Sanitary Sewer Fund 1,100,0001,100,000WF - Water Fund 2,200,000 2,200,000Total Wednesday, November 15, 2023 101 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact 2024 2028thru Department Public Works: Utilities Description Replacement of Lift Station no. 2 wetwell, controls and pumps Project #23-CIP-U021 Priority n/a Justification Based on observed site conditions, the wetwell, controls and pumps are beyone its service life. The lift station is not considered structurally sound in its current state. The detoriation rate will likely accelerate. The extensive pitting and crevice corrossion present may allow groundwater to leach into the structure. Budget Impact/Other Useful LifeProject Name Lift Station No. 2 Category Unassigned Type Improvement Future Total Project Cost:$250,000 Total20242025202620272028Expenditures 250,000250,000Construction/Maintenance 250,000 250,000Total Total20242025202620272028Funding Sources 250,000250,000WF - Water Fund 250,000 250,000Total Wednesday, November 15, 2023 102 CAPITAL IMPROVEMENT PLAN City of Hopkins, MN - CIP Contact 2024 2028thru Department Public Works: Utilities Description Switch current monitoring and controls equipment from radio communication to fiber communication. Project #23-CIP-U022 Priority n/a Justification Our current system of monitoring and controls can be vulnerable to hackers. Radio signals can be intercepted by unauthorized individuals using radio scanners or other devices. Our critical infrastructure will be safer with fiber. Budget Impact/Other Useful LifeProject Name SCADA Fiber Project Category Unassigned Type Improvement Future Total Project Cost:$750,000 Total20242025202620272028Expenditures 750,000350,000 400,000Construction/Maintenance 350,000 400,000 750,000Total Total20242025202620272028Funding Sources 375,000175,000 200,000SF - Sanitary Sewer Fund 375,000175,000 200,000WF - Water Fund 350,000 400,000 750,000Total Wednesday, November 15, 2023 103