Loading...
VII.1. Accept Bids and Award Contract; 2023 Street and Utility Improvements – City Project 2022-10; Klingbeil CITY OF HOPKINS City Council Report 2023-030 To: Honorable Mayor and Council Members Mike Mornson, City Manager From: Eric Klingbeil, City Engineer Date: March 21, 2023 Subject: Accept Bids and Award Contract; 2023 Street and Utility Improvements – City Project 2022-10 _____________________________________________________________________ RECOMMENDED ACTION MOTION TO Adopt Resolution 2023-014, Resolution Accepting Bids, 2023 Street and Utility Improvements, City Project 2022-10; and Adopt Resolution 2023-015, Resolution for Award of Contract, 2023 Street and Utility Improvements, City Project 2022-10. OVERVIEW The bid opening for the 2023 Street and Utility Improvements was February 10, 2023. The low bid for the base bid and all add alternates was submitted by Northwest Asphalt. The base bid was $5,784,476.25, the base bid with all add alternates was $6,219,375.97. A total of five (5) bids were received. Northwest Asphalt has a good reputation with previous similar projects in Hopkins and the wider metro area. Staff is recommending award of the project contract to Northwest Asphalt, including all add alternates. SUPPORTING INFORMATION Resolutions 2023-014, 2023-015 Consultant Recommendation Tabulation and Abstract of Bid Engineering ANALYSIS OF ISSUES Bid Results and Analysis Contractor Base Bid Base Bid+Add Alternates Northwest Asphalt $5,784,476.25 $6,219,375.97 Kuechle Underground $5,874,013.63 $6,304,149.56 Northdale Construction Company $6,518,416.36 $6,997,422.57 GMH Asphalt Corp $6,705,117.60 $7,136,405.53 Geislinger & Sons $6,756,108.10 $7,176,294.50 Engineers Estimate $6,003,451.00 $6,412,086.50 All bids were submitted with required bid security made by qualified contractors. Northwest Asphalt is reputable contractor who has completed similar projects in Hopkins and the wider metro area. Project Costs Based on the low bid the total estimated project cost is $7,150,000, which includes the low bid, all add alternates, and soft costs. The add alternates have no effect on the proposed assessment amounts. To capitalize on efficiencies and economies of scale, in addition to the add-alternates, additional work in and around the project area have been included in the project. These items will be paid for from their respective budgets. Bids received were lower than the Engineers Estimate, keeping the project, with all add alternates and additional work, under the budgeted amount. Amounts for individual funds are deviated slightly from the CIP budget; staff has worked with the Finance Director to account for the changes and ensure proper amounts and sources were considered for bond issuance. Due to favorable bid prices, staff is recommending to include all add-alternates with this project. By completing the street surface improvements in the add-alternate areas with this project, move invasive and costly improvements in the future can be avoided. The existing roadways are in such a condition that mill/overlay and reclamation are Funding Source CIP Budget Street Reconstruction Total Budget As-Bid Project Cost with Add Alternates PI-PIR/General Obligation Bonds $2,170,000 $2,778,000 $2,850,000 Assessments 1,050,000 1,050,000 1,070,000 Storm Sewer Fund 480,000 480,000 740,000 Sanitary Sewer Fund 1,363,000 1,448,000 1,180,000 Water Fund 1,430,000 1,430,00 1,310,000 Total $6,493,000 $7,186,000 $7,150,000 appropriate rehabilitation methods. Continued degradation of the road surface over time will require a full reconstruction. Project Schedule Conduct Public Assessment Hearing March 21, 2023 Adopt Assessment Roll/Award Contract March 21, 2023 Begin Construction Spring 2023 Complete Construction Fall 2023 CITY OF HOPKINS HENNEPIN COUNTY, MINNESOTA RESOLUTION 2023-014 RESOLUTION ACCEPTING BIDS 2023 STREET AND UTILITY IMPROVEMENTS CITY PROJECT 2022-10 WHEREAS, pursuant to an advertisement for bids for the improvement of 12th Avenue N from Mainstreet to 1st Street N, 14th Avenue N from Mainstreet to 2nd Street N, 15th Avenue N from Mainstreet to 2nd Street N, 16th Avenue N from Mainstreet to 1st Street N and 2nd Street N to 3rd Street N, and 2nd Street N from 14th Avenue N to 15th Avenue N, bids were received, opened, and tabulated according to law, and the following base bids were received complying with the advertisement: Northwest Asphalt $5,784,476.25 Kuechle Underground $5,874,013.63 Northdale Construction Company $6,518,416.36 GMH Asphalt Corp $6,705,117.60 Geislinger & Sons $6,756,108.10 AND WHEREAS, it appears that Northwest Asphalt of Shakopee, MN is the lowest responsible bidder, NOW THEREFORE BE IT RESOLVED, by the City Council of the City of Hopkins 1. The Mayor and City manager are hereby authorized and directed to enter a contract with Northwest Asphalt of Shakopee, MN in the name of the City of Hopkins for the improvements noted above according to the plans and specifications therefore approved by the city council and on file in the office of the city clerk. 2. The city clerk is hereby authorized and directed to return forthwith to all bidders the deposits made with their bids, except that the deposits of the successful bidder and the next lowest bidder shall be retained until a contract has been signed. Adopted by the City Council of the City of Hopkins this 21st day of March, 2023. By:___________________________ Patrick Hanlon, Mayor ATTEST: _______________________________ Amy Domeier, City Clerk CITY OF HOPKINS HENNEPIN COUNTY, MINNESOTA RESOLUTION 2023-015 RESOLUTION FOR AWARD OF CONTRACT 2023 STREET AND UTILITY IMPROVEMENTS CITY PROJECT 2022-10 WHEREAS, Bids for the 2023 Street and Utility Improvements, City Project 2022-10 have been accepted NOW THEREFORE BE IT RESOLVED, by the City Council of the City of Hopkins 1. That the base bid of Northwest Asphalt in the amount of $5,784,476.25 is the lowest responsible base bid for the 2023 Street and Utility Improvements, City Project 2022-10, and the Mayor and City Manager are hereby authorized and directed to enter into a contract with said bidder for and on behalf of the City. Adopted by the City Council of the City of Hopkins this 21st day of March, 2023. By:___________________________ Patrick Hanlon, Mayor ATTEST: _______________________________ Amy Domeier, City Clerk H:\HOPK\0T1127595\1_Corres\A_Meetings\2023-3-21_Council Mtg_Assessment Hearing\Hopkins 2023_Award Recommendation Letter.docx February 27, 2023 Mr. Eric Klingbeil, P.E., City Engineer City of Hopkins 1010 1st St S Hopkins, MN 55343 RE: 2023 Street & Utility Improvements City of Hopkins, Minnesota City Project No. 2022-10 Project No.: 0T1.127595 Dear Mr. Klingbeil, Bids on the above-referenced project were opened at 10:00 a.m. on February 10, 2023. There were five bidders for the project; a tabulation of bids received and a detailed bid abstract are enclosed. The low bidder on the project is Northwest Asphalt, Inc. with a bid of $5,784,476.25 for the base bid and $6,219,375 .97 for the base bid plus all three alternates. Northwest Asphalt, Inc. has previous experience on projects of this size and complexity in the City of Hopkins and elsewhere. Based on Northwest Asphalt’s experience, acceptable bid prices, and the competitive bids the City received, we recommend the City of Hopkins award the project , including all three alternates, to Northwest Asphalt, Inc. following the Public Assessment Hearing on March 21, 2023. If you have any questions regarding this award recommendation, please contact me at your convenience. Sincerely, Bolton & Menk, Inc. Nicholas J. Amatuccio, P.E. Associate Project Manager H:\HOPK\0T1127595\6_Plans-Specs\C_Bids Received\127595_Bid Tab.docx BID TABULATION 2023 Street & Utility Improvements City of Hopkins Hopkins , MN OT1.127595 Bid Taken: Friday, February 10, 2023 Addendums: 1 – January 31, 2023 Time: 10:00 a.m. BIDDERS BASE BID ALTERNATE 1 ALTERNATE 2 ALTERNATE 3 1 Northwest $5,784,476.25 $235,976.45 $56,086.98 $142,836.29 2 Kuechle Underground $5,874,013.63 $240,189.70 $48,498.15 $141,448.08 3 Northdale Construction Company $6,518,416.36 $255,611.66 $61,163.31 $162,231.24 4 GMH Asphalt $6,705,117.60 $245,692.03 $47,816.90 $137,779.00 5 Geislinger & Sons $6,756,108.10 $230,050.90 $47,738.50 $142,397.00 Hopkins, City of<BR>2023 Street & Utility Improvements<BR>0T1.127595 (#8357484) Owner: Hopkins MN, City of Solicitor: Bolton & Menk, Inc. 02/10/2023 10:00 AM CST 1 2 3 4 5 Engineer Estimate Section TitleLine Item Item Code Item Description UofM Quantity Unit Price Extension Unit Price Extension Unit Price Extension Unit Price Extension Unit Price Extension Unit Price Extension BASE BID 1 0 MOBILIZATION LUMP SUM 1 $300,000.00 $300,000.00 $198,130.00 $198,130.00 $71,000.00 $71,000.00 $130,650.00 $130,650.00 $440,000.00 $440,000.00 $287,000.00 $287,000.00 2 0 CLEARING TREE 45 $750.00 $33,750.00 $275.00 $12,375.00 $280.00 $12,600.00 $282.45 $12,710.25 $283.00 $12,735.00 $283.00 $12,735.00 3 0 GRUBBING TREE 53 $250.00 $13,250.00 $205.00 $10,865.00 $200.00 $10,600.00 $201.60 $10,684.80 $202.00 $10,706.00 $201.00 $10,653.00 4 0 TREE TRIMMING LUMP SUM 1 $10,000.00 $10,000.00 $5,000.00 $5,000.00 $12,000.00 $12,000.00 $4,494.00 $4,494.00 $4,515.00 $4,515.00 $4,500.00 $4,500.00 5 0 DECIDUOUS TREE 2" CAL B&B EACH 53 $600.00 $31,800.00 $535.00 $28,355.00 $500.00 $26,500.00 $393.75 $20,868.75 $655.00 $34,715.00 $400.00 $21,200.00 6 0 REMOVE SIGN POST EACH 49 $50.00 $2,450.00 $32.00 $1,568.00 $25.00 $1,225.00 $26.25 $1,286.25 $26.40 $1,293.60 $42.00 $2,058.00 7 0 REMOVE SIGN PANEL EACH 73 $50.00 $3,650.00 $26.00 $1,898.00 $25.00 $1,825.00 $26.25 $1,916.25 $26.40 $1,927.20 $42.00 $3,066.00 8 0 SALVAGE SIGN PANEL EACH 13 $55.00 $715.00 $26.00 $338.00 $40.00 $520.00 $42.00 $546.00 $42.20 $548.60 $42.00 $546.00 9 0 INSTALL SIGN PANEL EACH 13 $110.00 $1,430.00 $87.00 $1,131.00 $100.00 $1,300.00 $105.00 $1,365.00 $106.00 $1,378.00 $105.00 $1,365.00 10 0 REMOVE CURB AND GUTTER LIN FT 9860 $10.00 $98,600.00 $7.45 $73,457.00 $4.00 $39,440.00 $4.17 $41,116.20 $3.25 $32,045.00 $5.00 $49,300.00 11 0 REMOVE BITUMINOUS STREET PAVEMENT SQ YD 770 $10.00 $7,700.00 $9.50 $7,315.00 $4.00 $3,080.00 $7.81 $6,013.70 $6.00 $4,620.00 $5.00 $3,850.00 12 0 REMOVE BITUMINOUS DRIVEWAY/TRAIL PAVEMENT SQ YD 437 $10.00 $4,370.00 $12.00 $5,244.00 $4.00 $1,748.00 $7.81 $3,412.97 $8.25 $3,605.25 $5.00 $2,185.00 13 0 REMOVE CONCRETE WALK SQ YD 5550 $3.00 $16,650.00 $6.20 $34,410.00 $4.00 $22,200.00 $10.42 $57,831.00 $6.30 $34,965.00 $4.00 $22,200.00 14 0 REMOVE CONCRETE DRIVEWAY/ALLEY PAVEMENT SQ YD 1008 $12.00 $12,096.00 $9.40 $9,475.20 $4.00 $4,032.00 $13.02 $13,124.16 $17.85 $17,992.80 $7.00 $7,056.00 15 0 REMOVE CONCRETE STEP EACH 19 $45.00 $855.00 $56.00 $1,064.00 $100.00 $1,900.00 $156.25 $2,968.75 $180.00 $3,420.00 $150.00 $2,850.00 16 0 SALVAGE PAVERS SQ FT 506 $10.00 $5,060.00 $6.50 $3,289.00 $20.00 $10,120.00 $5.25 $2,656.50 $3.75 $1,897.50 $6.00 $3,036.00 17 0 SAWING CONCRETE PAVEMENT (FULL DEPTH)LIN FT 784 $5.00 $3,920.00 $5.00 $3,920.00 $3.00 $2,352.00 $3.17 $2,485.28 $3.35 $2,626.40 $6.00 $4,704.00 18 0 SAWING BITUMINOUS PAVEMENT (FULL DEPTH)LIN FT 1890 $4.00 $7,560.00 $4.00 $7,560.00 $3.00 $5,670.00 $2.16 $4,082.40 $2.28 $4,309.20 $5.00 $9,450.00 19 0 REMOVE RETAINING WALL LIN FT 121 $15.00 $1,815.00 $16.55 $2,002.55 $25.00 $3,025.00 $15.75 $1,905.75 $8.90 $1,076.90 $17.00 $2,057.00 20 0 SALVAGE & REINSTALL BOULDER WALL LIN FT 122 $75.00 $9,150.00 $50.57 $6,169.54 $104.00 $12,688.00 $69.30 $8,454.60 $69.95 $8,533.90 $70.00 $8,540.00 21 0 SALVAGE & REINSTALL STONE RETAINING WALL LIN FT 47 $100.00 $4,700.00 $182.37 $8,571.39 $230.00 $10,810.00 $94.50 $4,441.50 $129.00 $6,063.00 $95.00 $4,465.00 22 0 SALVAGE & REINSTALL BLOCK RETAINING WALL LIN FT 244 $150.00 $36,600.00 $136.00 $33,184.00 $160.00 $39,040.00 $75.60 $18,446.40 $75.35 $18,385.40 $78.00 $19,032.00 23 0 TIMBER RETAINING WALL LIN FT 22 $200.00 $4,400.00 $256.00 $5,632.00 $280.00 $6,160.00 $69.30 $1,524.60 $108.00 $2,376.00 $70.00 $1,540.00 24 0 MODULAR BLOCK RETAINING WALL SQ FT 390 $45.00 $17,550.00 $52.40 $20,436.00 $98.00 $38,220.00 $39.90 $15,561.00 $48.10 $18,759.00 $43.00 $16,770.00 25 0 SALVAGE LIGHT POLE EACH 2 $1,000.00 $2,000.00 $725.00 $1,450.00 $620.00 $1,240.00 $651.00 $1,302.00 $985.00 $1,970.00 $735.00 $1,470.00 26 0 REMOVE LIGHT POLE FOUNDATION EACH 2 $1,500.00 $3,000.00 $715.00 $1,430.00 $850.00 $1,700.00 $897.02 $1,794.04 $985.00 $1,970.00 $735.00 $1,470.00 27 0 REMOVE HYDRANT EACH 8 $750.00 $6,000.00 $168.46 $1,347.68 $330.00 $2,640.00 $520.83 $4,166.64 $798.00 $6,384.00 $150.00 $1,200.00 28 0 SALVAGE HYDRANT EACH 1 $1,000.00 $1,000.00 $192.52 $192.52 $470.00 $470.00 $781.25 $781.25 $1,595.00 $1,595.00 $1,000.00 $1,000.00 29 0 REMOVE WATERMAIN LIN FT 5570 $12.00 $66,840.00 $9.63 $53,639.10 $11.00 $61,270.00 $5.21 $29,019.70 $6.90 $38,433.00 $3.00 $16,710.00 30 0 REMOVE DRAINAGE STRUCTURE EACH 16 $500.00 $8,000.00 $385.05 $6,160.80 $580.00 $9,280.00 $781.25 $12,500.00 $553.00 $8,848.00 $300.00 $4,800.00 31 0 REMOVE STORM SEWER PIPE LIN FT 1059 $15.00 $15,885.00 $9.63 $10,198.17 $19.00 $20,121.00 $15.63 $16,552.17 $37.25 $39,447.75 $15.00 $15,885.00 32 0 REMOVE SANITARY SEWER PIPE LIN FT 4275 $10.00 $42,750.00 $7.70 $32,917.50 $11.00 $47,025.00 $2.08 $8,892.00 $4.25 $18,168.75 $3.00 $12,825.00 33 0 REMOVE SANITARY MANHOLE EACH 20 $750.00 $15,000.00 $385.05 $7,701.00 $580.00 $11,600.00 $781.25 $15,625.00 $1,340.00 $26,800.00 $350.00 $7,000.00 34 0 EXPLORATORY EXCAVATION HOUR 65 $1,000.00 $65,000.00 $1,030.00 $66,950.00 $830.00 $53,950.00 $1,562.50 $101,562.50 $213.00 $13,845.00 $1,000.00 $65,000.00 35 0 COMMON EXCAVATION (P)CU YD 18865 $22.00 $415,030.00 $24.02 $453,137.30 $21.00 $396,165.00 $36.55 $689,515.75 $37.05 $698,948.25 $28.00 $528,220.00 36 0 SUBGRADE EXCAVATION (EV)CU YD 1111 $30.00 $33,330.00 $26.00 $28,886.00 $20.00 $22,220.00 $36.55 $40,607.05 $37.05 $41,162.55 $30.00 $33,330.00 37 0 RECLAIM BITUMINOUS SURFACE SQ YD 17433 $2.50 $43,582.50 $3.26 $56,831.58 $2.50 $43,582.50 $3.13 $54,565.29 $2.50 $43,582.50 $5.00 $87,165.00 38 0 SELECT GRANULAR TRENCH BACKFILL TON 1000 $20.00 $20,000.00 $16.98 $16,980.00 $27.00 $27,000.00 $32.45 $32,450.00 $17.55 $17,550.00 $21.00 $21,000.00 39 0 GEOTEXTILE FABRIC TYPE V SQ YD 22161 $1.50 $33,241.50 $1.52 $33,684.72 $1.43 $31,690.23 $2.51 $55,624.11 $1.75 $38,781.75 $5.00 $110,805.00 40 0 STABILIZING AGGREGATE (CV)CU YD 1111 $50.00 $55,550.00 $23.00 $25,553.00 $52.00 $57,772.00 $74.93 $83,247.23 $39.50 $43,884.50 $34.60 $38,440.60 41 0 SELECT GRANULAR BORROW TON 13467 $18.00 $242,406.00 $17.10 $230,285.70 $18.00 $242,406.00 $22.03 $296,678.01 $17.30 $232,979.10 $19.00 $255,873.00 42 0 CLASS 5 AGGREGATE BASE TON 9072 $20.00 $181,440.00 $17.92 $162,570.24 $21.00 $190,512.00 $26.45 $239,954.40 $21.85 $198,223.20 $22.00 $199,584.00 43 0 CLASS 2 AGGREGATE SURFACING (GRAVEL DRIVEWAY)TON 16 $40.00 $640.00 $32.35 $517.60 $40.00 $640.00 $36.87 $589.92 $40.00 $640.00 $23.00 $368.00 44 0 BITUMINOUS WEARING COURSE (SPWEA240C)TON 1824 $90.00 $164,160.00 $90.45 $164,980.80 $87.00 $158,688.00 $91.56 $167,005.44 $95.60 $174,374.40 $105.00 $191,520.00 45 0 BITUMINOUS -NON-WEARING COURSE (SPNWB230C)TON 1824 $85.00 $155,040.00 $87.98 $160,475.52 $84.00 $153,216.00 $87.78 $160,110.72 $92.00 $167,808.00 $105.00 $191,520.00 46 0 BITUMINOUS WEARING COURSE (SPWEA340C)TON 413 $92.00 $37,996.00 $98.36 $40,622.68 $90.00 $37,170.00 $94.61 $39,073.93 $97.60 $40,308.80 $105.00 $43,365.00 47 0 BITUMINOUS -NON-WEARING COURSE (SPNWB330C)TON 383 $88.00 $33,704.00 $97.48 $37,334.84 $83.00 $31,789.00 $86.73 $33,217.59 $93.50 $35,810.50 $105.00 $40,215.00 48 0 BITUMINOUS MATERIAL FOR TACK COAT GAL 924 $5.00 $4,620.00 $7.50 $6,930.00 $3.15 $2,910.60 $3.31 $3,058.44 $4.80 $4,435.20 $3.50 $3,234.00 49 0 3" BITUMINOUS DRIVEWAY/TRAIL SQ YD 399 $30.00 $11,970.00 $27.10 $10,812.90 $38.00 $15,162.00 $60.17 $24,007.83 $29.90 $11,930.10 $30.00 $11,970.00 50 0 JOINT ADHESIVE (MASTIC)LIN FT 9800 $1.00 $9,800.00 $0.75 $7,350.00 $0.76 $7,448.00 $0.80 $7,840.00 $0.85 $8,330.00 $1.00 $9,800.00 51 0 6" PERF PVC UNDERDRAIN LIN FT 900 $20.00 $18,000.00 $23.39 $21,051.00 $14.00 $12,600.00 $44.40 $39,960.00 $17.45 $15,705.00 $21.00 $18,900.00 52 0 6" PVC UNDERDRAIN CLEANOUT EACH 18 $400.00 $7,200.00 $306.00 $5,508.00 $220.00 $3,960.00 $429.19 $7,725.42 $309.00 $5,562.00 $407.00 $7,326.00 53 0 12" RC STORM PIPE LIN FT 130 $50.00 $6,500.00 $68.09 $8,851.70 $73.00 $9,490.00 $85.54 $11,120.20 $89.90 $11,687.00 $105.00 $13,650.00 54 0 15" RC STORM PIPE LIN FT 905 $65.00 $58,825.00 $74.41 $67,341.05 $79.00 $71,495.00 $96.13 $86,997.65 $97.30 $88,056.50 $135.00 $122,175.00 55 0 24" RC STORM PIPE LIN FT 570 $95.00 $54,150.00 $98.88 $56,361.60 $110.00 $62,700.00 $119.75 $68,257.50 $132.00 $75,240.00 $160.00 $91,200.00 56 0 8" FLARED END SECTION W/ TRASH GUARD EACH 1 $1,300.00 $1,300.00 $374.26 $374.26 $1,100.00 $1,100.00 $630.09 $630.09 $384.00 $384.00 $740.00 $740.00 57 0 12" FLARED END SECTION W/ TRASH GUARD EACH 1 $1,300.00 $1,300.00 $412.33 $412.33 $3,000.00 $3,000.00 $1,933.02 $1,933.02 $2,004.00 $2,004.00 $1,960.00 $1,960.00 58 0 8" PVC DR18/HDPE DR11 STORM PIPE LIN FT 87 $65.00 $5,655.00 $60.17 $5,234.79 $78.00 $6,786.00 $78.05 $6,790.35 $71.25 $6,198.75 $78.00 $6,786.00 59 0 8" PVC DR18/HDPE DR11 (DIRECTIONALLY DRILLED)LIN FT 116 $175.00 $20,300.00 $149.48 $17,339.68 $190.00 $22,040.00 $123.70 $14,349.20 $178.00 $20,648.00 $150.00 $17,400.00 60 0 STORM MANHOLE (48-4020)EACH 11 $4,000.00 $44,000.00 $3,962.57 $43,588.27 $4,800.00 $52,800.00 $4,266.67 $46,933.37 $3,440.00 $37,840.00 $3,700.00 $40,700.00 61 0 STORM CATCH BASIN MANHOLE (48-4022)EACH 5 $4,000.00 $20,000.00 $3,214.31 $16,071.55 $4,800.00 $24,000.00 $4,051.67 $20,258.35 $3,007.00 $15,035.00 $3,400.00 $17,000.00 62 0 2'X3' STORM CATCH BASIN EACH 10 $2,000.00 $20,000.00 $2,174.98 $21,749.80 $2,600.00 $26,000.00 $3,060.52 $30,605.20 $1,825.00 $18,250.00 $2,500.00 $25,000.00 63 0 R-1733 STORM SEWER MANHOLE CASTING (SPECIAL)EACH 12 $1,200.00 $14,400.00 $987.00 $11,844.00 $1,800.00 $21,600.00 $1,358.69 $16,304.28 $1,381.00 $16,572.00 $781.00 $9,372.00 64 0 R-3067-V STORM SEWER CATCH BASIN CASTING EACH 16 $1,000.00 $16,000.00 $839.25 $13,428.00 $1,300.00 $20,800.00 $1,261.73 $20,187.68 $981.00 $15,696.00 $930.00 $14,880.00 65 0 R-3067-C STORM SEWER CATCH BASIN CASTING EACH 7 $1,000.00 $7,000.00 $893.25 $6,252.75 $1,300.00 $9,100.00 $1,315.48 $9,208.36 $1,041.00 $7,287.00 $980.00 $6,860.00 66 0 CONNECT TO EXISTING STORM PIPE EACH 11 $1,500.00 $16,500.00 $1,060.00 $11,660.00 $1,700.00 $18,700.00 $1,041.67 $11,458.37 $1,204.00 $13,244.00 $1,500.00 $16,500.00 Northwest Kuechle Underground Inc.Northdale Construction Company, Inc.GMH Asphalt Corporation Geislinger & Sons 67 0 CONNECT TO EXISTING DRAINAGE STRUCTURE EACH 13 $2,000.00 $26,000.00 $1,060.00 $13,780.00 $3,700.00 $48,100.00 $1,562.50 $20,312.50 $1,204.00 $15,652.00 $2,300.00 $29,900.00 68 0 8" PVC SDR 35 SANITARY SEWER PIPE LIN FT 3874 $65.00 $251,810.00 $53.25 $206,290.50 $68.00 $263,432.00 $66.08 $255,993.92 $78.20 $302,946.80 $122.00 $472,628.00 69 0 10" PVC SDR 35 SANITARY SEWER PIPE LIN FT 401 $75.00 $30,075.00 $80.15 $32,140.15 $110.00 $44,110.00 $85.83 $34,417.83 $85.35 $34,225.35 $150.00 $60,150.00 70 0 SANITARY POINT REPAIR EACH 4 $5,000.00 $20,000.00 $4,700.00 $18,800.00 $9,300.00 $37,200.00 $6,787.50 $27,150.00 $8,988.00 $35,952.00 $3,100.00 $12,400.00 71 0 COARSE AGGREGATE BEDDING (TYPE B)LIN FT 2000 $15.00 $30,000.00 $6.00 $12,000.00 $9.00 $18,000.00 $15.00 $30,000.00 $14.90 $29,800.00 $28.00 $56,000.00 72 0 8" CIPP LINING LIN FT 2181 $40.00 $87,240.00 $54.00 $117,774.00 $50.00 $109,050.00 $55.13 $120,238.53 $52.75 $115,047.75 $55.00 $119,955.00 73 0 10" CIPP LINING LIN FT 330 $45.00 $14,850.00 $56.16 $18,532.80 $52.00 $17,160.00 $52.82 $17,430.60 $54.85 $18,100.50 $53.00 $17,490.00 74 0 TRIM PROTRUDING TAP EACH 2 $500.00 $1,000.00 $432.00 $864.00 $400.00 $800.00 $225.86 $451.72 $422.00 $844.00 $227.00 $454.00 75 0 SEAL SANITARY MANHOLE EACH 9 $2,500.00 $22,500.00 $2,754.00 $24,786.00 $2,100.00 $18,900.00 $2,168.25 $19,514.25 $2,532.00 $22,788.00 $2,170.00 $19,530.00 76 0 6" PVC SDR 26 SANITARY SEWER SERVICE PIPE LIN FT 3887 $50.00 $194,350.00 $47.80 $185,798.60 $36.00 $139,932.00 $66.60 $258,874.20 $52.10 $202,512.70 $55.00 $213,785.00 77 0 6" PVC SDR 26 SANITARY SEWER SERVICE PIPE RISER LIN FT 346 $50.00 $17,300.00 $54.65 $18,908.90 $45.00 $15,570.00 $80.61 $27,891.06 $32.15 $11,123.90 $65.00 $22,490.00 78 0 8" X 6" SDR 26 PVC SERVICE WYE EACH 111 $650.00 $72,150.00 $833.70 $92,540.70 $1,300.00 $144,300.00 $550.21 $61,073.31 $1,005.00 $111,555.00 $2,200.00 $244,200.00 79 0 10"X6" SDR 26 PVC SERVICE WYE EACH 16 $800.00 $12,800.00 $989.70 $15,835.20 $1,800.00 $28,800.00 $694.33 $11,109.28 $1,160.00 $18,560.00 $2,400.00 $38,400.00 80 0 R-1733 SANITARY CASTING (SPECIAL)EACH 23 $1,500.00 $34,500.00 $1,194.00 $27,462.00 $1,800.00 $41,400.00 $1,364.07 $31,373.61 $1,372.00 $31,556.00 $931.00 $21,413.00 81 0 SANITARY MANHOLE LIN FT 253.8 $450.00 $114,210.00 $526.64 $133,661.23 $620.00 $157,356.00 $537.25 $136,354.05 $632.00 $160,401.60 $550.00 $139,590.00 82 0 RECONNECT SANITARY SEWER SERVICE EACH 129 $500.00 $64,500.00 $642.70 $82,908.30 $350.00 $45,150.00 $172.38 $22,237.02 $1,452.00 $187,308.00 $15.00 $1,935.00 83 0 CONNECT TO EXISTING SANITARY SEWER PIPE EACH 23 $2,000.00 $46,000.00 $1,144.00 $26,312.00 $460.00 $10,580.00 $1,696.88 $39,028.24 $1,951.00 $44,873.00 $2,800.00 $64,400.00 84 0 CONNECT TO EXISTING SANITARY MANHOLE EACH 1 $3,500.00 $3,500.00 $1,955.14 $1,955.14 $2,500.00 $2,500.00 $2,083.33 $2,083.33 $5,724.00 $5,724.00 $4,200.00 $4,200.00 85 0 HYDRANT EACH 8 $6,000.00 $48,000.00 $6,350.79 $50,806.32 $7,400.00 $59,200.00 $6,361.64 $50,893.12 $6,842.00 $54,736.00 $6,700.00 $53,600.00 86 0 HYDRANT EXTENSION EACH 4 $2,000.00 $8,000.00 $1,345.52 $5,382.08 $2,000.00 $8,000.00 $1,703.33 $6,813.32 $2,257.00 $9,028.00 $1,700.00 $6,800.00 87 0 REINSTALL SALVAGED HYDRANT EACH 1 $3,000.00 $3,000.00 $642.31 $642.31 $1,900.00 $1,900.00 $899.50 $899.50 $1,915.00 $1,915.00 $1,500.00 $1,500.00 88 0 INSTALL WATER SAMPLING STATION EACH 1 $1,000.00 $1,000.00 $609.05 $609.05 $3,500.00 $3,500.00 $1,761.38 $1,761.38 $1,808.00 $1,808.00 $1,100.00 $1,100.00 89 0 DUCTILE IRON FITTINGS POUND 4300 $12.00 $51,600.00 $10.81 $46,483.00 $16.00 $68,800.00 $14.32 $61,576.00 $11.70 $50,310.00 $10.10 $43,430.00 90 0 6" GATE VALVE & BOX EACH 16 $2,500.00 $40,000.00 $2,113.26 $33,812.16 $3,000.00 $48,000.00 $2,179.78 $34,876.48 $2,593.00 $41,488.00 $2,000.00 $32,000.00 91 0 8" GATE VALVE & BOX EACH 25 $3,000.00 $75,000.00 $2,912.33 $72,808.25 $3,700.00 $92,500.00 $3,002.04 $75,051.00 $3,363.00 $84,075.00 $2,700.00 $67,500.00 92 0 12" BUTTERFLY VALVE & BOX EACH 4 $4,500.00 $18,000.00 $5,755.92 $23,023.68 $6,400.00 $25,600.00 $5,538.93 $22,155.72 $6,082.00 $24,328.00 $5,000.00 $20,000.00 93 0 6" DIP WATERMAIN LIN FT 310 $70.00 $21,700.00 $67.62 $20,962.20 $73.00 $22,630.00 $93.54 $28,997.40 $96.80 $30,008.00 $75.00 $23,250.00 94 0 8" DIP WATERMAIN LIN FT 5233 $75.00 $392,475.00 $77.50 $405,557.50 $85.00 $444,805.00 $93.47 $489,128.51 $94.65 $495,303.45 $95.00 $497,135.00 95 0 12" DIP WATERMAIN LIN FT 67 $100.00 $6,700.00 $118.31 $7,926.77 $134.00 $8,978.00 $155.70 $10,431.90 $151.00 $10,117.00 $150.00 $10,050.00 96 0 1" TYPE K COPPER SERVICE PIPE LIN FT 3260 $55.00 $179,300.00 $45.02 $146,765.20 $37.00 $120,620.00 $65.78 $214,442.80 $46.80 $152,568.00 $55.00 $179,300.00 97 0 1" CURB STOP & BOX EACH 111 $500.00 $55,500.00 $756.54 $83,975.94 $670.00 $74,370.00 $545.29 $60,527.19 $688.00 $76,368.00 $1,300.00 $144,300.00 98 0 1" CORPORATION STOP EACH 111 $500.00 $55,500.00 $557.00 $61,827.00 $500.00 $55,500.00 $256.23 $28,441.53 $490.00 $54,390.00 $1,100.00 $122,100.00 99 0 POLYSTYRENE INSULATION (4" THICKNESS)SQ YD 200 $25.00 $5,000.00 $37.63 $7,526.00 $37.00 $7,400.00 $51.54 $10,308.00 $37.25 $7,450.00 $50.00 $10,000.00 100 0 GROUNDING ANODE EACH 111 $100.00 $11,100.00 $139.69 $15,505.59 $260.00 $28,860.00 $254.08 $28,202.88 $168.00 $18,648.00 $125.00 $13,875.00 101 0 TRACER WIRE ACCESS BOX (NON ROADWAY)EACH 111 $150.00 $16,650.00 $71.69 $7,957.59 $200.00 $22,200.00 $191.73 $21,282.03 $95.75 $10,628.25 $85.00 $9,435.00 102 0 TRACER WIRE TEST STATION (HYDRANT)EACH 9 $175.00 $1,575.00 $192.69 $1,734.21 $480.00 $4,320.00 $303.53 $2,731.77 $255.00 $2,295.00 $190.00 $1,710.00 103 0 FORD TYPE A-1 CURB BOX COVER EACH 36 $200.00 $7,200.00 $224.20 $8,071.20 $590.00 $21,240.00 $298.15 $10,733.40 $141.00 $5,076.00 $250.00 $9,000.00 104 0 RECONNECT WATER SERVICE EACH 115 $500.00 $57,500.00 $549.54 $63,197.10 $470.00 $54,050.00 $192.32 $22,116.80 $542.00 $62,330.00 $85.00 $9,775.00 105 0 CONNECT TO EXISTING WATERMAIN EACH 23 $1,200.00 $27,600.00 $1,416.00 $32,568.00 $4,000.00 $92,000.00 $1,992.50 $45,827.50 $2,429.00 $55,867.00 $3,000.00 $69,000.00 106 0 TEMPORARY WATER SERVICE EACH 116 $500.00 $58,000.00 $250.28 $29,032.48 $460.00 $53,360.00 $906.45 $105,148.20 $718.00 $83,288.00 $450.00 $52,200.00 107 0 TEMPORARY WATER SERVICE (SPECIAL)LUMP SUM 1 $10,000.00 $10,000.00 $17,808.41 $17,808.41 $25,000.00 $25,000.00 $20,833.33 $20,833.33 $19,411.00 $19,411.00 $15,000.00 $15,000.00 108 0 ADJUST GATE VALVE & BOX EACH 2 $500.00 $1,000.00 $850.00 $1,700.00 $330.00 $660.00 $520.83 $1,041.66 $772.00 $1,544.00 $250.00 $500.00 109 0 ADJUST CASTING EACH 12 $500.00 $6,000.00 $1,100.00 $13,200.00 $580.00 $6,960.00 $947.50 $11,370.00 $1,440.00 $17,280.00 $500.00 $6,000.00 110 0 4" CONCRETE WALK SQ FT 52225 $7.00 $365,575.00 $9.37 $489,348.25 $5.64 $294,549.00 $7.52 $392,732.00 $5.50 $287,237.50 $5.60 $292,460.00 111 0 CONCRETE STEP EACH 19 $350.00 $6,650.00 $510.00 $9,690.00 $450.00 $8,550.00 $262.50 $4,987.50 $486.00 $9,234.00 $266.00 $5,054.00 112 0 CONCRETE CURB & GUTTER DESIGN B618 LIN FT 9860 $22.00 $216,920.00 $16.84 $166,042.40 $17.00 $167,620.00 $20.58 $202,918.80 $17.80 $175,508.00 $20.00 $197,200.00 113 0 6" CONCRETE WALK (PEDESTRIAN RAMPS)SQ YD 360 $140.00 $50,400.00 $94.56 $34,041.60 $96.00 $34,560.00 $144.17 $51,901.20 $100.00 $36,000.00 $121.00 $43,560.00 114 0 6" CONCRETE DRIVEWAY SQ YD 559 $75.00 $41,925.00 $66.09 $36,944.31 $65.00 $36,335.00 $89.67 $50,125.53 $69.95 $39,102.05 $66.00 $36,894.00 115 0 8" CONCRETE DRIVEWAY/ALLEY SQ YD 626 $85.00 $53,210.00 $82.06 $51,369.56 $80.00 $50,080.00 $114.77 $71,846.02 $86.80 $54,336.80 $92.00 $57,592.00 116 0 TRUNCATED DOMES SQ FT 436 $60.00 $26,160.00 $63.00 $27,468.00 $62.00 $27,032.00 $55.40 $24,154.40 $66.90 $29,168.40 $53.00 $23,108.00 117 0 INSTALL PAVERS SQ FT 383 $20.00 $7,660.00 $14.20 $5,438.60 $30.00 $11,490.00 $12.60 $4,825.80 $14.80 $5,668.40 $17.00 $6,511.00 118 0 PORTABLE CHANGEABLE MESSAGE BOARDS UNIT DAY 40 $155.00 $6,200.00 $152.00 $6,080.00 $125.00 $5,000.00 $131.25 $5,250.00 $132.00 $5,280.00 $105.00 $4,200.00 119 0 TRAFFIC CONTROL LUMP SUM 1 $75,000.00 $75,000.00 $40,950.00 $40,950.00 $11,000.00 $11,000.00 $11,445.00 $11,445.00 $11,500.00 $11,500.00 $21,000.00 $21,000.00 120 0 TRAFFIC SIGN POST (ROUND W/ FOUNDATION)EACH 23 $350.00 $8,050.00 $455.00 $10,465.00 $570.00 $13,110.00 $593.25 $13,644.75 $596.00 $13,708.00 $367.00 $8,441.00 121 0 TRAFFIC SIGN POST (U-CHANNEL)EACH 25 $85.00 $2,125.00 $152.00 $3,800.00 $50.00 $1,250.00 $52.50 $1,312.50 $52.75 $1,318.75 $131.00 $3,275.00 122 0 SIGN PANEL (TYPE C)SQ FT 173 $25.00 $4,325.00 $45.00 $7,785.00 $62.00 $10,726.00 $65.10 $11,262.30 $65.40 $11,314.20 $53.00 $9,169.00 123 0 SIGN PANEL (TYPE D)SQ FT 84 $27.00 $2,268.00 $45.00 $3,780.00 $56.00 $4,704.00 $58.80 $4,939.20 $59.10 $4,964.40 $58.00 $4,872.00 124 0 RIGID PVC LOOP DETECTOR - 6'X6'EACH 4 $2,400.00 $9,600.00 $1,340.00 $5,360.00 $1,400.00 $5,600.00 $1,506.75 $6,027.00 $1,844.00 $7,376.00 $1,376.00 $5,504.00 125 0 LIGHT FOUNDATION - DESIGN E MODIFIED EACH 2 $1,250.00 $2,500.00 $1,650.00 $3,300.00 $1,400.00 $2,800.00 $1,422.75 $2,845.50 $2,252.00 $4,504.00 $1,680.00 $3,360.00 126 0 INSTALL LIGHT POLE EACH 2 $1,000.00 $2,000.00 $1,400.00 $2,800.00 $530.00 $1,060.00 $551.25 $1,102.50 $1,942.00 $3,884.00 $1,450.00 $2,900.00 127 0 1.5" NON-METALLIC LIGHTING CONDUIT LIN FT 135 $10.00 $1,350.00 $12.20 $1,647.00 $11.00 $1,485.00 $11.45 $1,545.75 $16.70 $2,254.50 $12.00 $1,620.00 128 0 3-1/C#4 LIGHTING WIRE LIN FT 145 $6.00 $870.00 $8.70 $1,261.50 $4.21 $610.45 $4.42 $640.90 $12.00 $1,740.00 $9.00 $1,305.00 129 0 LIGHTING GROUND WIRE LIN FT 145 $4.00 $580.00 $2.40 $348.00 $4.21 $610.45 $4.42 $640.90 $3.15 $456.75 $3.00 $435.00 130 0 LED LUMINAIRE EACH 2 $2,000.00 $4,000.00 $792.00 $1,584.00 $910.00 $1,820.00 $955.50 $1,911.00 $1,091.00 $2,182.00 $815.00 $1,630.00 131 0 STREET SWEEPER WITH OPERATOR HOUR 110 $150.00 $16,500.00 $145.00 $15,950.00 $170.00 $18,700.00 $141.75 $15,592.50 $158.00 $17,380.00 $200.00 $22,000.00 132 0 STABILIZED CONSTRUCTION EXIT EACH 4 $1,200.00 $4,800.00 $2,000.00 $8,000.00 $1,400.00 $5,600.00 $2,604.17 $10,416.68 $2,500.00 $10,000.00 $2,500.00 $10,000.00 133 0 STORM DRAIN INLET PROTECTION EACH 48 $200.00 $9,600.00 $180.00 $8,640.00 $740.00 $35,520.00 $260.42 $12,500.16 $112.00 $5,376.00 $150.00 $7,200.00 134 0 TOPSOIL BORROW (SPECIAL) (LV)CU YD 1343 $40.00 $53,720.00 $28.00 $37,604.00 $38.00 $51,034.00 $43.60 $58,554.80 $43.00 $57,749.00 $35.00 $47,005.00 135 0 HYDROMULCH & SEED MIX 25-151 SQ YD 2436 $3.00 $7,308.00 $2.10 $5,115.60 $1.75 $4,263.00 $2.78 $6,772.08 $2.11 $5,139.96 $3.00 $7,308.00 136 0 EROSION CONTROL BLANKET CATEGORY 20 & SEED MIX 25-151 SQ YD 1226 $10.00 $12,260.00 $3.65 $4,474.90 $1.95 $2,390.70 $3.94 $4,830.44 $2.11 $2,586.86 $4.00 $4,904.00 137 0 SILT FENCE - MACHINE SLICED LIN FT 1078 $5.00 $5,390.00 $2.10 $2,263.80 $2.25 $2,425.50 $2.89 $3,115.42 $2.11 $2,274.58 $3.00 $3,234.00 138 0 SEDIMENT CONTROL LOG (BIOROLL)LIN FT 556 $4.00 $2,224.00 $6.00 $3,336.00 $2.95 $1,640.20 $2.57 $1,428.92 $3.65 $2,029.40 $3.00 $1,668.00 139 0 RIPRAP CL. 2 (LV)CU YD 6 $75.00 $450.00 $117.76 $706.56 $125.00 $750.00 $156.25 $937.50 $165.00 $990.00 $100.00 $600.00 140 0 SODDING, TYPE LAWN SQ YD 9050 $8.00 $72,400.00 $8.05 $72,852.50 $13.00 $117,650.00 $6.25 $56,562.50 $13.20 $119,460.00 $6.25 $56,562.50 141 0 4" SOLID WHITE - MULTI COMPONET LIQUID LIN FT 95 $6.00 $570.00 $6.40 $608.00 $6.00 $570.00 $6.30 $598.50 $7.10 $674.50 $2.00 $190.00 142 0 CROSSWALK WHITE (6'X3' BLOCKS) - THERMOPLASTIC (GR IN)SQ FT 1566 $15.00 $23,490.00 $12.00 $18,792.00 $12.00 $18,792.00 $12.08 $18,917.28 $13.65 $21,375.90 $15.00 $23,490.00 143 0 LANDSCAPE ALLOWANCE LUMP SUM 1 $100,000.00 $100,000.00 $100,000.00 $100,000.00 $100,000.00 $100,000.00 $100,000.00 $100,000.00 $100,000.00 $100,000.00 $100,000.00 $100,000.00 TOTAL BASE BID $6,003,451.00 $5,784,476.25 $5,874,013.63 $6,518,416.36 $6,705,117.60 $6,756,108.10 ALTERNATE A A.1 0 MOBILIZATION LUMP SUM 1 $10,000.00 $10,000.00 $8,500.00 $8,500.00 $7,600.00 $7,600.00 $8,375.00 $8,375.00 $3,500.00 $3,500.00 $8,000.00 $8,000.00 A.2 0 REMOVE CURB AND GUTTER LIN FT 269 $10.00 $2,690.00 $12.00 $3,228.00 $4.00 $1,076.00 $10.42 $2,802.98 $10.50 $2,824.50 $4.00 $1,076.00 A.3 0 REMOVE BITUMINOUS STREET PAVEMENT SQ YD 788 $10.00 $7,880.00 $6.00 $4,728.00 $4.00 $3,152.00 $5.21 $4,105.48 $10.50 $8,274.00 $5.00 $3,940.00 A.4 0 REMOVE CONCRETE WALK SQ YD 293 $3.00 $879.00 $8.00 $2,344.00 $4.00 $1,172.00 $10.42 $3,053.06 $6.50 $1,904.50 $3.00 $879.00 A.5 0 SAWING CONCRETE PAVEMENT (FULL DEPTH)LIN FT 410 $5.00 $2,050.00 $5.00 $2,050.00 $3.00 $1,230.00 $5.15 $2,111.50 $3.35 $1,373.50 $6.00 $2,460.00 A.6 0 SAWING BITUMINOUS PAVEMENT (FULL DEPTH)LIN FT 386 $4.00 $1,544.00 $30.00 $11,580.00 $3.00 $1,158.00 $1.89 $729.54 $2.28 $880.08 $4.00 $1,544.00 A.7 0 REMOVE SIGN POST EACH 2 $50.00 $100.00 $26.00 $52.00 $25.00 $50.00 $26.25 $52.50 $26.40 $52.80 $42.00 $84.00 A.8 0 SALVAGE SIGN PANEL EACH 2 $55.00 $110.00 $26.00 $52.00 $40.00 $80.00 $42.00 $84.00 $42.20 $84.40 $42.00 $84.00 A.9 0 INSTALL SIGN PANEL EACH 2 $110.00 $220.00 $90.00 $180.00 $100.00 $200.00 $105.00 $210.00 $106.00 $212.00 $105.00 $210.00 A.10 0 TRAFFIC SIGN POST (U-CHANNEL)EACH 2 $70.00 $140.00 $158.00 $316.00 $50.00 $100.00 $52.50 $105.00 $52.75 $105.50 $128.00 $256.00 A.11 0 REMOVE CONCRETE PARKING STOP EACH 9 $100.00 $900.00 $50.00 $450.00 $100.00 $900.00 $52.08 $468.72 $100.00 $900.00 $150.00 $1,350.00 A.12 0 REMOVE DRAINAGE STRUCTURE EACH 2 $500.00 $1,000.00 $385.05 $770.10 $620.00 $1,240.00 $833.33 $1,666.66 $479.00 $958.00 $350.00 $700.00 A.13 0 REMOVE STORM SEWER PIPE LIN FT 61 $15.00 $915.00 $11.55 $704.55 $41.00 $2,501.00 $15.63 $953.43 $37.25 $2,272.25 $15.00 $915.00 A.14 0 REMOVE SANITARY SEWER PIPE LIN FT 25 $15.00 $375.00 $11.55 $288.75 $33.00 $825.00 $5.21 $130.25 $10.65 $266.25 $3.00 $75.00 A.15 0 REMOVE SANITARY MANHOLE EACH 1 $750.00 $750.00 $481.31 $481.31 $620.00 $620.00 $1,041.67 $1,041.67 $798.00 $798.00 $350.00 $350.00 A.16 0 EXPLORATORY EXCAVATION HOUR 5 $1,000.00 $5,000.00 $1,030.00 $5,150.00 $830.00 $4,150.00 $1,562.50 $7,812.50 $213.00 $1,065.00 $1,000.00 $5,000.00 A.17 0 COMMON EXCAVATION (P)CU YD 263 $22.00 $5,786.00 $28.58 $7,516.54 $22.00 $5,786.00 $36.46 $9,588.98 $45.00 $11,835.00 $32.00 $8,416.00 A.18 0 SUBGRADE EXCAVATION (EV)CU YD 79 $30.00 $2,370.00 $30.10 $2,377.90 $22.00 $1,738.00 $36.46 $2,880.34 $45.00 $3,555.00 $35.00 $2,765.00 A.19 0 STABILIZING AGGREGATE (CV)CU YD 79 $50.00 $3,950.00 $1.00 $79.00 $60.00 $4,740.00 $85.67 $6,767.93 $39.50 $3,120.50 $34.60 $2,733.40 A.20 0 CLASS 5 AGGREGATE BASE TON 321 $20.00 $6,420.00 $18.35 $5,890.35 $23.00 $7,383.00 $26.45 $8,490.45 $30.85 $9,902.85 $18.50 $5,938.50 A.21 0 BITUMINOUS WEARING COURSE (SPWEA340C)TON 469 $92.00 $43,148.00 $99.20 $46,524.80 $92.00 $43,148.00 $97.02 $45,502.38 $96.65 $45,328.85 $113.00 $52,997.00 A.22 0 BITUMINOUS -NON-WEARING COURSE (SPNWB330C)TON 95 $88.00 $8,360.00 $115.36 $10,959.20 $120.00 $11,400.00 $127.05 $12,069.75 $188.30 $17,888.50 $113.00 $10,735.00 A.23 0 BITUMINOUS MATERIAL FOR TACK COAT GAL 324 $5.00 $1,620.00 $7.50 $2,430.00 $4.50 $1,458.00 $4.73 $1,532.52 $6.00 $1,944.00 $3.50 $1,134.00 A.24 0 2" BITUMINOUS STREET PATCH SQ YD 410 $25.00 $10,250.00 $22.18 $9,093.80 $27.00 $11,070.00 $49.04 $20,106.40 $36.50 $14,965.00 $21.00 $8,610.00 A.25 0 MILL BITUMINOUS SURFACE (1.5")SQ YD 2911 $2.00 $5,822.00 $1.95 $5,676.45 $2.60 $7,568.60 $3.05 $8,878.55 $3.00 $8,733.00 $2.00 $5,822.00 A.26 0 MILL BITUMINOUS SURFACE (2")SQ YD 1173 $2.00 $2,346.00 $2.21 $2,592.33 $2.90 $3,401.70 $3.05 $3,577.65 $3.50 $4,105.50 $3.00 $3,519.00 A.27 0 JOINT ADHESIVE (MASTIC)LIN FT 1950 $1.00 $1,950.00 $1.28 $2,496.00 $1.00 $1,950.00 $1.05 $2,047.50 $0.85 $1,657.50 $1.00 $1,950.00 A.28 0 12" RC STORM PIPE LIN FT 19 $65.00 $1,235.00 $71.00 $1,349.00 $117.00 $2,223.00 $98.00 $1,862.00 $144.00 $2,736.00 $90.00 $1,710.00 A.29 0 STORM MANHOLE (72-4020)EACH 1 $6,000.00 $6,000.00 $24,322.00 $24,322.00 $9,800.00 $9,800.00 $15,917.50 $15,917.50 $19,362.00 $19,362.00 $15,660.00 $15,660.00 A.30 0 R-1733 STORM SEWER MANHOLE CASTING (SPECIAL)EACH 1 $1,200.00 $1,200.00 $987.00 $987.00 $1,800.00 $1,800.00 $1,364.33 $1,364.33 $1,382.00 $1,382.00 $781.00 $781.00 A.31 0 ADJUST CASTING EACH 2 $750.00 $1,500.00 $845.00 $1,690.00 $1,300.00 $2,600.00 $901.01 $1,802.02 $1,440.00 $2,880.00 $500.00 $1,000.00 A.32 0 CONNECT TO EXISTING STORM PIPE EACH 5 $1,500.00 $7,500.00 $1,060.00 $5,300.00 $3,500.00 $17,500.00 $1,562.50 $7,812.50 $1,330.00 $6,650.00 $2,150.00 $10,750.00 A.33 0 CONNECT TO EXISTING STORM STRUCTURE EACH 2 $2,000.00 $4,000.00 $1,060.00 $2,120.00 $5,700.00 $11,400.00 $2,083.33 $4,166.66 $1,330.00 $2,660.00 $2,920.00 $5,840.00 A.34 0 R-1733 SANITARY CASTING (SPECIAL)EACH 2 $1,500.00 $3,000.00 $1,194.00 $2,388.00 $1,800.00 $3,600.00 $1,364.33 $2,728.66 $1,372.00 $2,744.00 $931.00 $1,862.00 A.35 0 8" PVC SDR 35 SANITARY SEWER PIPE LIN FT 25 $65.00 $1,625.00 $51.29 $1,282.25 $150.00 $3,750.00 $98.34 $2,458.50 $125.00 $3,125.00 $115.00 $2,875.00 A.36 0 CONNECT TO EXISTING SANITARY SEWER PIPE EACH 2 $2,000.00 $4,000.00 $1,100.00 $2,200.00 $3,600.00 $7,200.00 $1,627.00 $3,254.00 $2,127.00 $4,254.00 $2,725.00 $5,450.00 A.37 0 SANITARY MANHOLE LIN FT 8.8 $450.00 $3,960.00 $554.26 $4,877.49 $660.00 $5,808.00 $631.21 $5,554.65 $762.00 $6,705.60 $650.00 $5,720.00 A.38 0 ADJUST GATE VALVE & BOX EACH 3 $500.00 $1,500.00 $645.00 $1,935.00 $640.00 $1,920.00 $364.59 $1,093.77 $759.00 $2,277.00 $200.00 $600.00 A.39 0 4" CONCRETE WALK SQ FT 1680 $7.00 $11,760.00 $9.44 $15,859.20 $6.18 $10,382.40 $10.21 $17,152.80 $5.50 $9,240.00 $8.00 $13,440.00 A.40 0 CONCRETE CURB & GUTTER DESIGN B618 LIN FT 281 $30.00 $8,430.00 $32.20 $9,048.20 $32.00 $8,992.00 $30.77 $8,646.37 $34.05 $9,568.05 $30.00 $8,430.00 A.41 0 6" CONCRETE WALK (PEDESTRIAN RAMPS)SQ YD 57 $140.00 $7,980.00 $100.55 $5,731.35 $93.00 $5,301.00 $162.54 $9,264.78 $100.00 $5,700.00 $135.00 $7,695.00 A.42 0 TRUNCATED DOMES SQ FT 60 $60.00 $3,600.00 $64.00 $3,840.00 $60.00 $3,600.00 $55.63 $3,337.80 $66.90 $4,014.00 $53.00 $3,180.00 A.43 0 TRAFFIC CONTROL LUMP SUM 1 $10,000.00 $10,000.00 $4,200.00 $4,200.00 $950.00 $950.00 $997.50 $997.50 $1,002.00 $1,002.00 $525.00 $525.00 A.44 0 STREET SWEEPER WITH OPERATOR HOUR 16 $150.00 $2,400.00 $145.00 $2,320.00 $170.00 $2,720.00 $141.75 $2,268.00 $158.00 $2,528.00 $200.00 $3,200.00 A.45 0 STORM DRAIN INLET PROTECTION EACH 10 $200.00 $2,000.00 $180.00 $1,800.00 $740.00 $7,400.00 $260.42 $2,604.20 $112.00 $1,120.00 $150.00 $1,500.00 A.46 0 4" SOLID WHITE - MULTI COMPONET LIQUID LIN FT 300 $1.50 $450.00 $6.35 $1,905.00 $6.00 $1,800.00 $6.30 $1,890.00 $7.10 $2,130.00 $2.00 $600.00 A.47 0 4" BROKEN YELLOW - MULTI COMPONET LIQUID LIN FT 200 $0.75 $150.00 $2.20 $440.00 $2.00 $400.00 $2.10 $420.00 $2.37 $474.00 $2.00 $400.00 A.48 0 CROSSWALK WHITE (6'X3' BLOCKS) - THERMOPLASTIC (GR IN)SQ FT 486 $15.00 $7,290.00 $12.08 $5,870.88 $11.00 $5,346.00 $12.08 $5,870.88 $13.65 $6,633.90 $15.00 $7,290.00 TOTAL ALTERNATE A $216,155.00 $235,976.45 $240,189.70 $255,611.66 $245,692.03 $230,050.90 ALTERNATE B B.1 0 MOBILIZATION LUMP SUM 1 $10,000.00 $10,000.00 $7,545.00 $7,545.00 $4,600.00 $4,600.00 $8,375.00 $8,375.00 $3,000.00 $3,000.00 $1,500.00 $1,500.00 B.2 0 REMOVE CURB AND GUTTER LIN FT 90 $10.00 $900.00 $18.00 $1,620.00 $10.00 $900.00 $10.42 $937.80 $10.50 $945.00 $4.00 $360.00 B.3 0 REMOVE CONCRETE WALK SQ YD 74 $3.00 $222.00 $14.00 $1,036.00 $10.00 $740.00 $10.42 $771.08 $6.50 $481.00 $3.00 $222.00 B.4 0 SAWING CONCRETE PAVEMENT (FULL DEPTH)LIN FT 60 $5.00 $300.00 $4.00 $240.00 $4.00 $240.00 $5.15 $309.00 $3.35 $201.00 $6.00 $360.00 B.5 0 MILL BITUMINOUS SURFACE (1.5")SQ YD 1698 $2.00 $3,396.00 $2.97 $5,043.06 $2.95 $5,009.10 $3.58 $6,078.84 $4.50 $7,641.00 $2.00 $3,396.00 B.6 0 2" BITUMINOUS STREET PATCH SQ YD 170 $25.00 $4,250.00 $22.90 $3,893.00 $32.00 $5,440.00 $53.66 $9,122.20 $36.50 $6,205.00 $23.00 $3,910.00 B.7 0 BITUMINOUS WEARING COURSE (SPWEA340C)TON 154 $92.00 $14,168.00 $105.23 $16,205.42 $93.00 $14,322.00 $97.23 $14,973.42 $96.65 $14,884.10 $121.00 $18,634.00 B.8 0 BITUMINOUS MATERIAL FOR TACK COAT GAL 119 $5.00 $595.00 $7.50 $892.50 $4.75 $565.25 $4.99 $593.81 $6.00 $714.00 $3.50 $416.50 B.9 0 JOINT ADHESIVE (MASTIC)LIN FT 960 $1.00 $960.00 $2.70 $2,592.00 $2.15 $2,064.00 $2.26 $2,169.60 $0.85 $816.00 $1.00 $960.00 B.10 0 R-1733 SANITARY CASTING (SPECIAL)EACH 1 $1,500.00 $1,500.00 $1,200.00 $1,200.00 $1,800.00 $1,800.00 $1,364.33 $1,364.33 $1,372.00 $1,372.00 $931.00 $931.00 B.11 0 4" CONCRETE WALK SQ FT 485 $7.00 $3,395.00 $5.30 $2,570.50 $6.18 $2,997.30 $10.21 $4,951.85 $5.50 $2,667.50 $8.00 $3,880.00 B.12 0 CONCRETE CURB & GUTTER DESIGN B618 LIN FT 90 $30.00 $2,700.00 $33.76 $3,038.40 $32.00 $2,880.00 $35.86 $3,227.40 $34.05 $3,064.50 $35.00 $3,150.00 B.13 0 8" CONCRETE DRIVEWAY/ALLEY SQ YD 20 $85.00 $1,700.00 $95.33 $1,906.60 $80.00 $1,600.00 $159.39 $3,187.80 $86.80 $1,736.00 $132.00 $2,640.00 B.14 0 TRAFFIC CONTROL LUMP SUM 1 $5,000.00 $5,000.00 $4,200.00 $4,200.00 $350.00 $350.00 $367.50 $367.50 $369.00 $369.00 $525.00 $525.00 B.15 0 STREET SWEEPER WITH OPERATOR HOUR 10 $150.00 $1,500.00 $145.00 $1,450.00 $170.00 $1,700.00 $141.75 $1,417.50 $158.00 $1,580.00 $200.00 $2,000.00 B.16 0 STORM DRAIN INLET PROTECTION EACH 3 $200.00 $600.00 $180.00 $540.00 $740.00 $2,220.00 $260.42 $781.26 $112.00 $336.00 $150.00 $450.00 B.17 0 TOPSOIL BORROW (SPECIAL) (LV)CU YD 16 $40.00 $640.00 $42.00 $672.00 $38.00 $608.00 $46.87 $749.92 $48.30 $772.80 $44.00 $704.00 B.18 0 HYDROMULCH & SEED MIX 25-151 SQ YD 150 $3.00 $450.00 $8.15 $1,222.50 $1.75 $262.50 $10.50 $1,575.00 $5.30 $795.00 $22.00 $3,300.00 B.19 0 4" BROKEN YELLOW - MULTI COMPONET LIQUID LIN FT 100 $0.75 $75.00 $2.20 $220.00 $2.00 $200.00 $2.10 $210.00 $2.37 $237.00 $4.00 $400.00 TOTAL ALTERNATE B $52,351.00 $56,086.98 $48,498.15 $61,163.31 $47,816.90 $47,738.50 ALTERNATE C C.1 0 MOBILIZATION LUMP SUM 1 $10,000.00 $10,000.00 $8,140.00 $8,140.00 $7,500.00 $7,500.00 $10,160.00 $10,160.00 $3,500.00 $3,500.00 $3,500.00 $3,500.00 C.2 0 REMOVE CURB AND GUTTER LIN FT 248 $10.00 $2,480.00 $12.50 $3,100.00 $10.00 $2,480.00 $10.42 $2,584.16 $10.50 $2,604.00 $4.00 $992.00 C.3 0 REMOVE BITUMINOUS STREET PAVEMENT SQ YD 11 $10.00 $110.00 $12.00 $132.00 $10.00 $110.00 $10.42 $114.62 $50.00 $550.00 $4.00 $44.00 C.4 0 REMOVE CONCRETE WALK SQ YD 194 $3.00 $582.00 $8.20 $1,590.80 $5.00 $970.00 $10.42 $2,021.48 $6.50 $1,261.00 $3.00 $582.00 C.5 0 SAWING CONCRETE PAVEMENT (FULL DEPTH)LIN FT 174 $5.00 $870.00 $5.00 $870.00 $3.00 $522.00 $5.15 $896.10 $3.35 $582.90 $6.00 $1,044.00 C.6 0 SAWING BITUMINOUS PAVEMENT (FULL DEPTH)LIN FT 40 $4.00 $160.00 $5.00 $200.00 $3.00 $120.00 $1.89 $75.60 $2.28 $91.20 $5.00 $200.00 C.7 0 BITUMINOUS WEARING COURSE (SPWEA340C)TON 474 $92.00 $43,608.00 $98.40 $46,641.60 $92.00 $43,608.00 $97.13 $46,039.62 $96.65 $45,812.10 $121.00 $57,354.00 C.8 0 BITUMINOUS MATERIAL FOR TACK COAT GAL 366 $5.00 $1,830.00 $7.50 $2,745.00 $3.25 $1,189.50 $3.41 $1,248.06 $6.00 $2,196.00 $3.50 $1,281.00 C.9 0 2" BITUMINOUS STREET PATCH SQ YD 534 $25.00 $13,350.00 $17.10 $9,131.40 $27.00 $14,418.00 $48.93 $26,128.62 $36.50 $19,491.00 $22.00 $11,748.00 C.10 0 MILL BITUMINOUS SURFACE (1.5")SQ YD 5226 $2.00 $10,452.00 $1.46 $7,629.96 $2.65 $13,848.90 $3.05 $15,939.30 $2.50 $13,065.00 $2.50 $13,065.00 C.11 0 JOINT ADHESIVE (MASTIC)LIN FT 2483 $1.00 $2,483.00 $1.25 $3,103.75 $1.00 $2,483.00 $1.05 $2,607.15 $0.85 $2,110.55 $1.00 $2,483.00 C.12 0 MONOFORM MANHOLE REHABILITATION (STORM)LIN FT 11.2 $650.00 $7,280.00 $1,605.00 $17,976.00 $450.00 $5,040.00 $467.25 $5,233.20 $788.00 $8,825.60 $470.00 $5,264.00 C.13 0 REPAIR STORM SEWER MANHOLE INVERT EACH 1 $5,000.00 $5,000.00 $1,030.00 $1,030.00 $3,700.00 $3,700.00 $1,562.50 $1,562.50 $1,330.00 $1,330.00 $2,550.00 $2,550.00 C.14 0 R-1733 STORM SEWER MANHOLE CASTING (SPECIAL)EACH 1 $1,200.00 $1,200.00 $1,194.00 $1,194.00 $1,800.00 $1,800.00 $1,364.33 $1,364.33 $1,382.00 $1,382.00 $781.00 $781.00 C.15 0 R-1733 SANITARY CASTING (SPECIAL)EACH 2 $1,500.00 $3,000.00 $1,194.00 $2,388.00 $1,800.00 $3,600.00 $1,364.33 $2,728.66 $1,372.00 $2,744.00 $931.00 $1,862.00 C.16 0 4" CONCRETE WALK SQ FT 1201 $7.00 $8,407.00 $6.00 $7,206.00 $6.18 $7,422.18 $10.21 $12,262.21 $5.50 $6,605.50 $8.00 $9,608.00 C.17 0 CONCRETE CURB & GUTTER DESIGN B618 LIN FT 248 $30.00 $7,440.00 $33.76 $8,372.48 $32.00 $7,936.00 $30.77 $7,630.96 $34.05 $8,444.40 $30.00 $7,440.00 C.18 0 8" CONCRETE DRIVEWAY/ALLEY SQ YD 60 $85.00 $5,100.00 $93.18 $5,590.80 $80.00 $4,800.00 $159.39 $9,563.40 $86.80 $5,208.00 $132.00 $7,920.00 C.19 0 TRAFFIC CONTROL LUMP SUM 1 $5,000.00 $5,000.00 $4,200.00 $4,200.00 $850.00 $850.00 $892.50 $892.50 $897.00 $897.00 $525.00 $525.00 C.20 0 STREET SWEEPER WITH OPERATOR HOUR 8 $150.00 $1,200.00 $145.00 $1,160.00 $170.00 $1,360.00 $141.75 $1,134.00 $158.00 $1,264.00 $200.00 $1,600.00 C.21 0 STORM DRAIN INLET PROTECTION EACH 15 $200.00 $3,000.00 $180.00 $2,700.00 $740.00 $11,100.00 $260.42 $3,906.30 $112.00 $1,680.00 $150.00 $2,250.00 C.22 0 TOPSOIL BORROW (SPECIAL) (LV)CU YD 16 $40.00 $640.00 $42.00 $672.00 $38.00 $608.00 $46.87 $749.92 $48.30 $772.80 $44.00 $704.00 C.23 0 HYDROMULCH & SEED MIX 25-151 SQ YD 150 $3.00 $450.00 $8.15 $1,222.50 $1.75 $262.50 $10.50 $1,575.00 $5.30 $795.00 $22.00 $3,300.00 C.24 0 HANDICAP SYMBOL (GR IN) - THERMOPLASTIC EACH 1 $750.00 $750.00 $505.00 $505.00 $500.00 $500.00 $519.75 $519.75 $587.00 $587.00 $220.00 $220.00 C.25 0 4" SOLID WHITE - MULTI COMPONET LIQUID LIN FT 55 $1.50 $82.50 $6.40 $352.00 $6.00 $330.00 $6.30 $346.50 $7.10 $390.50 $2.00 $110.00 C.26 0 4" BROKEN YELLOW - MULTI COMPONET LIQUID LIN FT 120 $0.75 $90.00 $2.20 $264.00 $2.00 $240.00 $2.10 $252.00 $2.37 $284.40 $2.00 $240.00 C.27 0 4" SOLID YELLOW - MULTI COMPONET LIQUID LIN FT 165 $1.00 $165.00 $2.20 $363.00 $2.00 $330.00 $2.10 $346.50 $2.37 $391.05 $2.00 $330.00 C.28 0 CROSSWALK WHITE (6'X3' BLOCKS) - THERMOPLASTIC (GR IN)SQ FT 360 $15.00 $5,400.00 $12.10 $4,356.00 $12.00 $4,320.00 $12.08 $4,348.80 $13.65 $4,914.00 $15.00 $5,400.00 TOTAL ALTERNATE C $140,129.50 $142,836.29 $141,448.08 $162,231.24 $137,779.00 $142,397.00 BASE BID TOTAL $6,003,451.00 $5,784,476.25 $5,874,013.63 $6,518,416.36 $6,705,117.60 $6,756,108.10 ALTERNATE A $216,155.00 $235,976.45 $240,189.70 $255,611.66 $245,692.03 $230,050.90 ALTERNATE B $52,351.00 $56,086.98 $48,498.15 $61,163.31 $47,816.90 $47,738.50 ALTERNATE C $140,129.50 $142,836.29 $141,448.08 $162,231.24 $137,779.00 $142,397.00 GRAND TOTAL BASE BID AND ALTERNATES $6,412,086.50 $6,219,375.97 $6,304,149.56 $6,997,422.57 $7,136,405.53 $7,176,294.50 ENG EST Northwest Kuechle Underground Inc.Northdale Construction Company, Inc.GMH Asphalt Corporation Geislinger & Sons